The ridge and hips above a Swainshill cottage
Two slopes meet along the ridge, the high line of the roof, and a Swainshill survey begins there. The top of the roof carries a row of capping tiles, set in mortar or else clipped and screwed down as a dry-fix system. Walk the whole length from gable to gable and the faults show. Press on a capping tile and, if it rocks, its bed has gone. Where the mortar in a joint has crumbled, rain runs in at the gap and onto the top course, and from the loft a line of daylight along the ridge points to an open joint.
Breinton parish, which takes in Swainshill, has its own entry in the Royal Commission on Historical Monuments' 1932 inventory of Herefordshire. For monuments 3 to 8 it described buildings that "are of the 17th century and of two storeys, timber-framed and with tiled or slate-covered roofs". That wording matters when you stand under a ridge, because the covering may be clay tile, natural slate or a later replacement, and the capping and fixing differ for each. We find out which you have before we say what to do.
A ridge tile that rocks is a bedding repair, and we price it as exactly that.
On fixing, Marley states that "Installing to BS 5534 isn't required by law", and adds that mortar "could no longer be relied upon as the only means of securing the roof covering". BS 5534:2014+A2:2018 is the standard that governs how slates and tiles are fixed. Dry-fix systems come under BS 8612, and mortar itself is still allowed. On a ridge we rebed, each capping tile is mechanically fixed as well, and an older house can keep its mortar-bedded look where the building calls for it.
Hips are the angled outer corners at which two slopes meet. Each hip has its own run of capping and its own joint with the main ridge, so we check where all the lines meet. Photographs from the top of the ladder come to you: the gable end tiles, the mortar joints and any gap under a capping tile.
Fixing a loose ridge is repair work and is quoted as repair work. Where the survey finds a covering at the close of its working life, a heavier material is the main trap. The Planning Portal sets the line: a new covering that "increases the weight of the roof covering by 15 per cent or more" needs approval, with a structural check first. Smaller jobs are covered on our roof repairs page.
Checked along the Swainshill ridge
- Rocking or lifted capping tiles
- Crumbled or cracked mortar joints
- A fixing on every capping tile
- Hip junctions with the main ridge
- End tiles at each gable
Ridge fixing in outline
- Bedded ridge
- Capping set in mortar, with a fixing added to each tile
- Dry-fix ridge
- Clips and screws, under BS 8612
- Hip capping
- A separate run, joined to the main ridge