In brief
MyJobQuote (page dated 22/09/26) gives about £200 for patching the lead flashing at a chimney and about £570 for replacing it in full. Checkatrade (June 2026, excluding VAT) lists lead flashing repairs at £50 to £70 per metre. Both are typical UK figures from other firms' pages, never a Horizon price. What we write for your roof is a single total, fixed after we have looked at the lead from the roof and the loft.
What the published guides say about lead flashing
Flashing means the lead dressed over the joint where a roof meets a chimney stack or a gable wall, so that rain cannot get into the gap. The wider lead roofing page covers the other places lead is used on a house. Two cost guides publish figures for flashing, and they measure different things, so the numbers cannot simply be set side by side without a little care.
| Job | Figure |
|---|---|
| Patch repair to the flashing | around £200 |
| Full replacement, average | around £570 |
| Full leadwork, range | £350 to £920 |
Those three are totals for a chimney job. Checkatrade's rate is a different kind of number: £50 to £70 per metre for lead flashing repairs, and its page says VAT will need to be added to its costs. MyJobQuote does not state its VAT basis on that page, so ask any firm whether VAT sits inside the price. A rate per metre never turns into a total for your roof, because nobody knows the run of lead until it has been measured on site.
What moves a flashing job up or down
MyJobQuote's own words are that full chimney leadwork costs between £350 and £920, "depending largely on whether scaffolding is required". A gap that wide tells you the house matters more than the method. At the survey we look at:
- how many metres of flashing the job runs to, and whether it is one chimney or a long wall abutment
- whether the lead is split in one spot or lifting along its whole length
- the condition of the brick or stone joints it is tucked into, since lead cannot hold in crumbling mortar
- whether slates or tiles beside it have to be lifted to reach the lead
- how high the work is, and whether a ladder gives safe access
- the thickness of lead the detail calls for, covered in what lead code is used for flashings
A flashing at a bungalow porch is a different morning's work from the same flashing three storeys up on a stack with a back gutter behind it. Our photographs of your own flashing show which kind of job you have, before any price is written down.
When a patch is enough and when it is not
A patch suits lead that is sound apart from one defect: a single split, a short lifted edge or a small hole. The damaged piece is cut out or covered, and the rest of the run stays put. It costs less because less lead and less time are involved, and when a patch is the better buy we tell you.
Replacement is the honest answer when the lead is cracking in several places, has lifted along the whole joint, or has been smeared with sealant over the years so that its true condition is hidden. Lead patched again and again can cost more in the end than one proper job.
Age alone is not the test. On the MyJobQuote page, flashing in lead that has been fitted correctly "can last for over 80 years". That is a hedged claim, never a promise, so an old flashing that is still flat and unsplit may need nothing at all. The page on how long lead flashing lasts goes through what shortens that life, and repairing old leadwork sets out the repairs themselves.
Scaffold, VAT and the single written price
Scaffold can swing a leadwork price, so a quote should say whether it is in. Where the scaffold would stand on the road or pavement, we arrange the licence with our scaffolder. Councils set their own fees, each in its own unit, and each wants notice before the poles go up:
- In England, Herefordshire Council's fee is £167 for a maximum of one month, £123 for each further month, with at least 10 days' notice.
- In Wales, the Monmouthshire licence has an administration fee of £108, then £27 per week to extend, and the council asks for 5 working days' notice at least.
Whatever scaffold we need sits inside the one written total, so it never arrives as a surprise on a later invoice. Put the same two questions to every firm: is VAT in the figure, and is scaffold in the figure. A quote that answers both on paper can be set against another that does the same.
Our figure is a single total, not a rate per metre. If the job is a short patch reached from a ladder, the total says so and carries no scaffold at all.