Valley leadwork

Lead valley gutters: boards, laps and fillets

A lead valley gutter lines the fold where two roof slopes meet. This guide follows it layer by layer, from the boards under the sheet to the laps and fillets that finish the edges.

Horizon Roofing Hereford 9 min read

A valley is the line where two roof slopes run down into each other, so water off both of them collects on it. A lead valley gutter is a channel of sheet lead laid along that line, with the tiles or slates to either side stopping short of the centre so the metal stays open to the sky. It carries the water of two slopes down to the eaves, which makes it work harder than any single flashing on the roof.

Four parts make up the detail, and the sections below take them in order: the boards the lead lies on, the sheet itself, the laps where one length overlaps the next, and the fillets and edges where the lead meets the covering. A fault in a lead valley sits in one of those parts or in the joint beside it, so a survey reads them in that order and photographs each.

The guide also reads Royston's code table for valley work, lists what sets the price of a job, and shows how England and Wales part ways once a valley repair grows into a larger re-roof. Our lead roofing page covers the wider range of leadwork we fit and repair.

The boards the lead lies on

Lead sheet is soft, and it takes the shape of whatever lies beneath it. A valley therefore starts with timber: boards fixed between the rafters or over them along the whole length of the valley, with the surface planed true. Any dip or step in the boards becomes a dip or step in the metal, and a dip is where water lingers and a fold begins to crack.

The boards are also where an old valley gives its worst news. A lead channel that has leaked for a season lets rain soak into the timber below it, and soft or blackened boards cannot hold new lead flat. Relaying sheet over rotten boards would only bury the problem, so the first job in any valley renewal is to open the channel and look.

Along the sides of the channel there can be timber battens or strips on which the edges of the lead rest. These are the fillets covered in a later section, and they are fixed to the boards at this stage too.

When we open a valley, we check and photograph:

  • whether the boards are dry, firm and flat along the full length
  • the rafters and wall plate beneath them for stains or soft patches
  • the underlay at the edges, which can be torn where the old lead was cut back
  • the state of the nails, since rust shows how long water has been present
  • the boards beside any chimney or dormer the valley runs past

You see those photographs before any price is agreed, so the verdict on the boards rests on pictures of your own valley, not on a guess from the ground.

Choosing the lead code for a valley

Lead sheet comes in codes numbered 3 to 8, with thickness and weight rising up the scale. Royston Lead's cast lead brochure sets out which uses each code is listed for, and valley gutters sit in two of its groups. A pitched valley gutter, the plain fold between two sloping roofs, is listed for Codes 4, 5, 6, 7 and 8. A tapered valley gutter, which narrows along its length, falls in the parapet, box and tapered group, listed for Codes 5, 6, 7 and 8.

Valley uses and the codes Royston lists for them
Valley useCodes listed
Pitched valley gutter4, 5, 6, 7 and 8
Tapered valley gutter5, 6, 7 and 8
Soakers beside the valley3 and 4

The table narrows the choice but does not make it. Within a range of five codes, the choice turns on how long the valley runs, the catchment of roof behind it and the way the valley is built. Royston's thickest listed sheet, Code 8, is 3.55mm and weighs 40.26 kg per m²; Code 4 is 1.80mm at 20.41 kg per m². The thick sheet is more than twice the weight on the same boards.

A written quote for a valley should say which code is going in and why. Royston also gives each code a colour as well as a number, which helps when two rolls sit side by side on a scaffold.

Laps, drips and how a long valley is joined

A valley may not run short enough to be lined with a single piece of sheet, so the lining is made of lengths that overlap. The overlap is called a lap, and its direction matters: each upper length lies over the one below it, so the water runs down across the join and never into it. Reverse a lap and the valley leaks in the first heavy shower.

To make room for the laps, the boards are stepped. Each step is called a drip, and it lowers the surface by a small amount so the next length can lap over the last without lifting. The drips also break a long run into stages, so water slows slightly at each one and the lead is not asked to hold an unbroken sheet for the whole length.

That second point is the reason for the joins. Lead moves as it warms and cools, and a very long, unbroken sheet moves further than a short one. Where the sheet cannot move freely, it creeps and then splits along the fold or at a fixing. A valley with no drips and one huge sheet is a valley to look at closely.

On a survey, we look along the run for:

  • laps that face the wrong way or have lifted at the edge
  • splits across the centre line, where the sheet has flexed
  • cracks beside the nails or clips that hold the upper edge
  • patches of solder or mastic where an earlier repair was made

Our guide to why a lead valley leaks takes the common faults one by one.

Fillets, edges and the covering beside the lead

The edges of a valley are where the lead meets the roof covering, and they decide whether the channel stays clear. A fillet is a strip of timber, triangular in section, fixed along each side of the valley under the edge of the lead. It lifts the edge of the sheet and holds the first course of covering just clear of the channel, so a strip of bare metal is left open down the middle.

The lead is dressed up and over the fillet and tucked under the covering. How far it tucks in and how wide the open channel is both affect how the valley copes with a heavy downpour. A narrow channel clogs with moss and leaf litter; a channel packed too tight can back water up under the covering at the edge. These are measured on the roof, not copied from a drawing.

Where a Herefordshire valley runs between stone-tiled slopes, the tilestones are local sandstone, with the St Maughans sandstones around the Golden Valley named as the principal source in the atlas of county building stone that Herefordshire Council hosts. SPAB calls Welsh slate and stone roofs "predominantly double-lapped". A valley between two such slopes has to be cut with the stone's thickness and its double lap in mind, and a stone edge needs more careful bedding on the fillet than a thin slate does.

Where a valley meets a chimney, a wall or a dormer cheek, the lead of the valley passes into a flashing or a back gutter. Our guide to the back gutter behind a chimney covers that meeting point, which is where two pieces of leadwork have to be tied together.

What sets the price of a valley job

This section explains what sits behind the total in a written quote. No two valleys are the same job, and a short valley on a low roof is different work from a long one on a three-storey house.

The items that move the price:

  • the length of the valley and the area of roof that sheds into it
  • the lead code chosen, since thicker sheet costs more and weighs more
  • how much of the board bed needs replacing
  • the height of the roof and the way the valley is reached
  • whether the covering beside the valley has to be lifted and relaid
  • whether the valley meets other leadwork that also needs work

Access matters more than people expect. MyJobQuote, in its leadwork page last updated on 22 September 2026, gives full leadwork of between £350 and £920 "depending largely on whether scaffolding is required". That figure is for chimney leadwork, so it is no guide to a valley price, but it shows how much of a lead price can come from the height and the way in. Check that any quote you hold states whether scaffold and VAT are included. Ours carries the scaffold it needs inside the one total.

Where a valley is sound apart from a split or a lifted lap, mending it costs less than relining, and that is the job we recommend. Where the boards are rotten or the lead has given up along the run, we show you the photographs and explain why a patch would not hold.

When a valley repair meets the building rules

Relining one valley is a repair. Once the work spreads to the covering on either side, the border line decides which rule reads.

  • England: the Planning Portal sets two tests together. No application is normally needed where "Less than 25 per cent of the total 'building envelope'" is affected and "Less than 50 per cent of the roof is affected". A heavier new covering is a separate trigger: the Portal says approval follows where it "increases the weight of the roof covering by 15 per cent or more".
  • Wales: the Welsh Government states of re-roofing that "In most situations, this work will need Building Regulations approval." Its separate roof page draws a line at "less than 25 per cent of the area of a pitch or flat roof" for repairs or re-covering without an application, and expects better roof insulation above that line.

Relining a single valley and relaying the tiles beside it is a small part of a whole roof. A wider re-cover is a different calculation, made on the roof itself.

Before work reaches the size where either rule bites, we ask building control, meaning the council's building control team or a registered building control approver, whichever your address calls for.

A listed house adds a second layer. In England the consent rule is s7 of the Planning (Listed Buildings and Conservation Areas) Act 1990. Wales has its own statute, the Historic Environment (Wales) Act 2023, where s88 and s89 apply. Our guide to step, apron and cover flashings shows how a neighbouring flashing ties into the same covering.

Valley gutters: your questions

Can a split in a lead valley be patched without relaying the whole channel?

A lone split in sound lead on firm boards can be repaired in place. A split in a sheet that has creeped along its length, or boards that are soft beneath it, points to relining. We photograph the split and the boards, show you both, and give one written total price for whichever fits.

Why does a valley gutter sit lower than the tiles beside it?

The channel gathers the run-off from both slopes, so its lead runs between the two edges and tucks beneath the covering on each side. Tiles or slates stand proud on the fillets, which lift the edge of the sheet and keep a clear strip of metal open down the middle.

How do I know which lead code my valley was laid in?

A lead roll or sheet is stamped with its code, and Royston's table gives each code a colour, thickness and weight. On an existing valley, a code is read by measuring the sheet's thickness in millimetres at a cut edge. We measure at the survey and write the code into the quote for a replacement.