Walk round the outside of an older house and the lead tells you a lot. Along the side of a chimney the lead is cut in a staircase of small steps. Across the bottom of the stack it lies flat in one wide strip. Above both, a narrow band of lead hangs down from the brickwork like a lip. These are the step flashing, the apron flashing and the cover flashing, and each has a different job. Flashing means a strip of sheet metal, lead in this case, that seals the gap where a roof meets anything standing up from it, whether a dormer cheek, a gable wall or a stack.
A leak beside a chimney can be traced to one of these three, and the fault may not be the sheet of lead itself. It sits at the edge of the lead, where it tucks into the wall, or in the join between two pieces. Knowing which flashing you are looking at tells you where to look first.
This guide takes the three in turn, then covers the way the lead is held in the wall, which lead codes are listed for flashings, and where the border changes the rules once a repair grows. For the whole range of leadwork we take on, see our lead roofing page.
Three flashings, three different jobs
The easiest way to tell the three apart is to ask which way the water is travelling when it reaches the wall. Rain runs down a roof slope, so it meets a chimney from three directions at once. On the uphill side it arrives head on. On the downhill side it leaves the roof and runs past the stack. Along the sides it runs beside the wall rather than towards it. Each direction needs a different shape of lead.
The step flashing handles the sides, where the wall rises up through the slope. The apron flashing handles the downhill face, where water pours off the roof and meets the base of the stack. The cover flashing is the upper layer: a strip that tucks into the wall and hangs over another piece of lead, a soaker or a roof upstand, so the joint beneath is shielded from above. A cover flashing is what you see over the turned-up edge of a flat roof where it meets a house wall, and above the lead lining of a dormer cheek. On a chimney, the uphill side can take a back gutter instead, which our guide to the back gutter behind a chimney covers.
| Flashing | Where it sits | Its job |
|---|---|---|
| Step | Along a wall rising through the slope | Follows the roof line in stepped pieces |
| Apron | Across the foot of a stack or wall | Carries water from the wall onto the covering |
| Cover | Over a soaker, upstand or other lead | Shields the joint beneath from rain above |
One stack can carry all three, which is why a patch on one side does not always cure a stain inside.
How a step flashing follows the slope
A wall that rises through a sloping roof cannot take one straight strip of lead, because the roof runs downhill beneath it while the brick courses stay level. The step flashing solves this by cutting the upper edge of the lead into a series of steps, each step sitting in a mortar joint of the wall. As the roof falls away, the lead steps down with it, following the brickwork.
Under a tiled or slated roof, the lower edge of the lead is not lying on top of the covering. It is worked into the courses, so each tile or slate laps over the lead and sheds water onto the roof below. In the classic arrangement, a small folded piece called a soaker sits under each course, and the stepped lead above it covers the vertical face. Our guide to lead soakers under tiles and slates explains that half of the detail.
The stepping is what makes the flashing hard to supply as a stock product. Every house has its own tile size, its own brick course height and its own slope, so the pieces are cut to the wall in front of us. When a stepped flashing is renewed, the work runs in this order:
- strip the old lead and the loose mortar in the joints it sat in
- check the battens and the underlay behind it, which may be damp by this stage
- fit the soakers or the lower lead course by course as the tiles go back
- form and fix each step, then point the joints
The checks behind the lead are the part a look from the garden cannot do, and they are why we photograph the open joint before anything new goes in.
Aprons at the foot of the stack
An apron flashing is the single wide piece of lead that lies across the bottom of a chimney, or along the foot of any wall that stands at the bottom of a slope. Rain running down the roof meets the stack here and has nowhere to go but sideways, so the apron has to carry it round and onto the covering. The top edge turns up the face of the wall; the lower edge lies over the tiles, slates or stone and is dressed down to follow their surface.
An apron makes sense on a chimney because the water arrives on the downhill side in a sheet. It also appears wherever a lean-to or an extension roof butts into the wall of the main house. Our guide to lead where an extension meets the house deals with that arrangement.
Aprons let go in a few predictable ways:
- the top edge lifts out of the wall where the pointing has loosened
- the lower edge curls up and lets rain run under it
- a split opens at a fold where the metal has worked back and forth
- a seam parts where a long run was made from too few pieces
Sheet lead grows and shrinks with the temperature, so a long run is built from shorter lengths with lapped joints rather than one continuous sheet. The same movement is why a wide apron needs room to slide beneath its fixings. A flashing pinned hard at every point will split sooner than one fixed to move.
Chases, wedges and pointing where the lead meets the wall
All three flashings depend on the same detail at the wall: the lead has to be held tight in a joint and kept dry behind. A chase is a groove cut into the wall, along a mortar joint, to take the upper edge of the lead. The edge is turned into the chase, held with lead wedges and then pointed, which means the joint is filled back with mortar so rain cannot enter behind the lead. A cover flashing hangs from exactly this kind of joint.
This stage varies more with the house than any other. In the Herefordshire Building Stone Atlas, the stacks on the black-and-white houses are "commonly of local sandstone". A sandstone stack has joints of uneven depth and softer edges than brick, so the chase may need to follow the stone rather than a neat line. On an older house the pointing is chosen to match the mortar already in the wall, because a harder mix can damage the stone beside it.
When we look at a lifted flashing, our questions are:
- is the lead tucked into the chase, or only stuck to the surface of the wall
- are the wedges still in place, or has the lead dropped out of its joint
- has the pointing cracked or washed away above the lead
- is there any sign of the wall itself breaking up behind the lead
Mastic run along the upper edge may disguise a lifted flashing for a season, yet it only masks the joint and does not repair it. We open the joint, refit the lead and point it, so the wall holds the lead rather than the sealant.
Lead codes for flashings, and how long they last
Roofing lead comes in numbered codes, from 3 to 8, and the code is a measure of thickness. The Royston Lead brochure lists the uses for each. Code 3, at 1.32 mm, is marked "Recommended for lead soakers only". Codes 4, 5 and 6 are listed for flashings, with code 4 at 1.80 mm, code 5 at 2.24 mm and code 6 at 2.65 mm. The choice between them depends on the flashing and the wall it sits against.
| Code | Thickness | Listed uses include |
|---|---|---|
| 3 | 1.32 mm | Soakers only |
| 4 | 1.80 mm | Soakers, flashings, valleys, dormers |
| 5 | 2.24 mm | Flashings, valleys, parapets, dormers |
| 6 | 2.65 mm | Flashings, valleys, parapets, dormers |
BS 6229 deals with membranes, so lead falls outside it, and AD C names BS 6915 for lead. A flashing is judged on how it sheds water and how well it is fixed.
On lifespan, MyJobQuote says correctly installed lead flashing "can last" for over 80 years. That is a hedged statement from a cost guide, not a promise, and it depends on the fixing and the state of the wall around the lead.
On cost, MyJobQuote (page updated September 2026) puts a patch repair to chimney leadwork at around £200 and a full replacement at around £570, and full leadwork anywhere from £350 to £920, with the difference mostly down to scaffolding. Checkatrade (June 2026, ex VAT) puts lead flashing repairs at £50 to £70 per metre. Both are ranges from third parties, never ours.
Repair or renew, and what changes across the border
A single lifted flashing is a repair. Where the lead has split along several folds, or the wall behind it is crumbling, renewing the whole run is the better buy, and the photographs show why. The side of the border starts to matter once the work grows into re-covering the roof around the lead:
- In England, the Planning Portal sets two tests: no application is normally needed where "Less than 25 per cent of the total 'building envelope'" is affected and "Less than 50 per cent of the roof is affected."
- In England, the Planning Portal also lists a new covering that adds weight "by 15 per cent or more" as work that needs approval.
- In Wales, the Welsh Government writes of re-roofing: "In most situations, this work will need Building Regulations approval."
Before a job of that size starts, and before any lead is ordered, we ask the building control team on your side of the border, which may be the council or a registered building control approver.
Reading the photographs together makes the choice plain. A flashing with one lifted edge and sound pointing around it is a refit. A flashing that has split at several folds, sits in a crumbling joint or has been patched with sealant more than once is a renewal, and we would rather show you that on screen than ask you to take it on trust.
A flashing high on a chimney needs access, and the cost of leadwork swings with it. Where the scaffold stands on the public highway, the Highways Act 1980 s169 applies, and we arrange the licence with our scaffolder. Check that any quote you hold says whether the scaffold and VAT are in it.