In brief
No. BS 6229 sets out good practice for flat roofs that carry a flexible waterproof membrane over a continuous deck, and the 2025 edition is the current one. Lead sheet falls outside it. In England, Approved Document C names a different standard for lead, BS 6915:2001. So the 1:80 finished fall quoted from BS 6229 belongs to membrane roofs, not to a lead roof.
What BS 6229:2025 covers
BS 6229:2025 is the current edition. BSI lists the 2018 edition as withdrawn on 16 December 2025, so a quote or a specification that still cites BS 6229:2018 is working from a superseded document.
The scope is narrow. BSI describes it as covering "flat roofs (or curved roofs with a pitch not greater than 10 degrees)" that use "continuously supported flexible waterproof coverings". Continuously supported means the covering lies on a deck across its whole area, and flexible waterproof coverings are the membrane family. Sheet metal is a different material with its own habits over laps, falls and movement, and the standard does not claim to deal with it. A builder who quotes a lead roof "to BS 6229" is therefore using a label that does not fit, and the quote is worth querying.
One figure from the 2025 edition is widely repeated. The NFRC says it sets "a minimum 1:80 finished fall for general roof areas and internal gutters". A finished fall is the gradient left on the roof when the job is done, after the deck has settled and the covering is down, and it can differ from the gradient drawn on the plan. IKO, a membrane maker, advises designing for 1:40 so that 1:80 is reached as built.
Which document deals with lead instead
For lead, Building Regulations guidance points elsewhere. The documents that come up in lead and flat-roof conversations each have a scope of their own:
- BS 6229:2025: membrane roofs that are flat or gently curved, up to 10 degrees of pitch
- BS 6915:2001: the standard that Approved Document C cites for lead in England
- BS 5534:2014+A2:2018: the standard behind fixing tiles and slates on pitched roofs, which Marley says "isn't required by law"
Marley's remark about BS 5534 is a reminder that a British Standard is a document of good practice before it is anything else. Which standard a building control body expects on a given job is a question for that body, and we ask it before work that touches the structure of a roof.
The lead codes themselves come from the maker's table and not from BS 6229. Royston Lead lists Code 4 to Code 8 for the larger lead details, and Code 3 for soakers only, with a use letter against each code, so the sheet for each detail can be checked against a published list.
A lead flat roof or a flashing: what follows
A lead flat roof is not specified as a membrane roof, so the 1:80 figure is not a number to hold a lead roof to. The falls on a lead roof are worked out at the survey, from the shape of the roof and where the water has to go, and they are recorded in the quote where you can read them.
The same applies to the other lead details on a house. In Royston's table, use letter D covers the box, parapet and tapered valley gutters, and it is listed against Codes 5, 6, 7 and 8. Flashings take Codes 4, 5 or 6. Our pages on parapet and box gutters in lead and how long a lead flat roof lasts go into the detail.
If you are weighing lead against a membrane on a flat roof, ask each quote for three things: the falls, the code of sheet and the standard the work follows. Those answers show whether two quotes describe the same job or two different ones, and they put the comparison on the roof itself and not on the headline price. A lead roof and a membrane roof are each a good answer in the right place, and they are priced and detailed differently.
Who to ask about a standard in England and Wales
Standards that sit behind the Building Regulations are a matter for building control, and the route to an answer depends on which side of the border the house stands.
- In England, Approved Document C (2013) cites BS 6915:2001 for lead. For a Herefordshire address, Herefordshire Council Building Control is on 01432 261938, and a registered building control approver is the private route.
- In Wales, ask the council's building control service, or a registered building control approver, which standard they expect for lead on your roof.
A repair works the same way. A new flashing on one chimney is a small job, yet the approval rules for re-roofing are judged on the whole roof, so the position is checked before a larger lead job begins and the answer is written down. Standards sit alongside those rules and do not replace them, which is why the question goes to building control and not to the lead supplier.