A terraced house does not own its roof in the way a detached house does. The party walls between the houses run up beside the slopes, a chimney stack can sit astride the line between two homes, and a repair at the boundary touches a neighbour's property as well as your own. Slate laid in the Victorian period can still be in good order on such a roof, so the question may not be the slates themselves. It is the joints where the roofs meet.
Three details deserve the closest look: the valleys where two roofs meet, the stacks that rise from the party wall, and the abutments where slate stops against masonry. Each is lead-lined or lead-flashed, and each sits at or near the boundary. That is also where the Party Wall etc. Act 1996 comes in, an Act that reaches terraces in Herefordshire and in Monmouthshire alike.
The sections below take the roof as we survey it, from the boundary outwards, and then the notices, the scaffold licence and the approval rules. For the wider subject, see our slate roofing page.
Where a terrace roof differs from a detached one
On a detached house, every edge of the roof is yours. On a terrace, the roof of each house meets its neighbours at party walls, and what happens at that line is shared. The slate stops against masonry, the masonry belongs to both houses, and a flashing set into it serves both roofs. A fault in one house can therefore show up as damp in the next.
We survey a terrace roof in a different order for that reason. We look first along the boundary line from the ridge down, at what the party wall does where it meets the roof, and at any stack that sits on it. Then we look at any valley, where the roof of a rear projection or an extension runs into the main slope. Only after that do we move to the open slopes and the roofline.
What we note on the first visit:
- where the party wall meets the slate, and how the joint is sealed
- whether a stack sits on the boundary line or wholly on one side
- whether a valley carries water from more than one roof
- whether work on the neighbouring roof has altered the shared joint
- how scaffold or a ladder could reach the work from the street
The photographs go with the quote, and a joint that is shared is marked as shared, so you can see which parts of the job are yours alone and which need a conversation with next door.
A terrace can be re-roofed one house at a time. Where the neighbour has already re-covered, the join between their new work and your old slates is a joint of its own, and we look at how it was made before relying on it.
Valleys: where two roofs meet
A valley is the angle where two slopes run together, with a lead-lined channel along the join. The slates are cut to follow its edges, and the channel carries the water of both slopes down to the eaves. A fault there shows quickly, because everything the two slopes shed passes through it.
Royston Lead's table lists the lead codes by use. Pitched valley gutters take Code 4, 5, 6, 7 or 8, and Code 3 is "Recommended for lead soakers only". Soakers are thin folded pieces of lead, interleaved with the slates where they meet a wall or stack. MyJobQuote's line is that correctly installed lead flashing "can last for over 80 years", and that describes a sound installation, not every old valley.
| Part | What it does | What we check |
|---|---|---|
| Valley gutter | Carries water from two slopes | Splits, lifted edges, debris |
| Soakers | Seal slate against a wall | Slipped or corroded pieces |
| Flashing | Covers the soaker line | Pointing, lifting, gaps |
Our guide to lead details on a slate roof covers each in more detail. A lining that has split along its length needs the neighbouring slates lifted so it can be replaced, and the sound slates go back on new fixings.
The edges of a lining sit under the slates on either side, so the check includes lifting a slate or two beside the valley to see them. We photograph what is under there before anything is closed up again.
Stacks on the party wall
A chimney stack that rises from the party wall serves the fireplaces of two houses. Above the slates, it is a tall masonry column exposed on every face. Its pointing, its flaunching (the cement or lime collar set round the pots) and the lead flashings at its foot all need to be sound, and a fault at any of them can wet the rooms of both houses.
The stack is reached from the roof on your side, but its foot sits at the boundary. Taking the stack down, or cutting away a breast in the rooms below, is bigger work than repointing. MyJobQuote's averages are around £200 for a lead patch at a chimney, around £570 for replacing the flashing in full and around £2,500 for removing a chimney breast. Those are UK averages, not prices for any house.
The Planning Portal says "Building regulations approval will always apply when removing chimney breasts as they are part of the building's structure." For a breast on a party wall, the Party Wall etc. Act 1996 applies as well, as the next section sets out.
Our guide to chimneys on a party wall goes through the stack itself. On a terrace the stack deserves a place in the survey even when the slates are sound, because a stack that leans or sheds its pointing can drop debris onto a neighbour's roof as well as your own.
Party walls: who serves which notice
The Party Wall etc. Act 1996 is a statute whose notice periods are the same across both countries. The building owner, meaning the person for whom the work is done, serves it, never the roofer or the neighbour:
| Work | Notice | Section |
|---|---|---|
| Cutting away a chimney breast or a footing | At least two months | s2(2)(g), s3(2)(a) |
| Building on the line of junction, or digging nearby | At least one month | s1, s6 |
Section 2(2)(j) gives the right "to cut into the wall of an adjoining owner's building in order to insert a flashing or other weather-proofing of a wall erected against that wall", which is the sort of work an abutment on a terrace can involve. Under section 3(3)(a), a neighbour can give consent in writing.
If the neighbour does not answer within 14 days, section 5 treats that as dissent, a dispute is deemed to exist, and surveyors are appointed under section 10. Silence is never read as agreement.
Whether a given roof job is party wall work is for a party wall surveyor to say, not building control. The survey marks where our plan touches the boundary, so that any notice goes out early.
The three roles stay separate. The surveyor settles a dispute if one arises, we deal with the roof, and building control has its own part under the Building Regulations.
Scaffold on the street, and the licence
Many terraces front the pavement, and scaffold put up over the road or pavement calls for a licence under section 169 of the Highways Act 1980. The notice period is built into the programme, and we arrange the licence with our scaffolder. The council that issues it sets its own fee and notice, so the figures belong to the street:
- Herefordshire Council: £167 is for a maximum of 1 month, each extension is £123 per month, and 10 days' notice is the minimum.
- Monmouthshire County Council: £108 as an administration fee, £27 per week to extend, with 5 working days of notice or more.
The two cannot be compared like for like, because the units differ. For a house in another council's area we check that council's own page before the job is priced, and the written quote covers the scaffold.
A scaffold on a terrace also stands close to a neighbour's wall and windows, so we agree access with them early where the plan needs it. That conversation is easier before the notice than after.
Rear access matters too. It differs from one terrace to the next, with an alley behind, a passage between houses or neither, and that changes how materials are lifted and how waste is taken away. The survey records which applies, with photographs, so that the price reflects the real route and the site is left clear when the work ends.
Re-slating a terrace: the rules country by country
Re-covering a slope follows the rules of whichever country the house is in:
- In England, the Planning Portal's tests are "Less than 25 per cent of the total 'building envelope'" and "Less than 50 per cent of the roof"; it does not expect a Building Regulations application inside both.
- In Wales, the Welsh Government's wording for re-roofing is: "In most situations, this work will need Building Regulations approval."
Neither set of rules answers a party wall question. Those go to a party wall surveyor.
A street of Victorian houses may lie in a conservation area. Herefordshire has 64 conservation areas, and the council can tell you whether yours is one. We also check whether an Article 4 direction applies with the council before a covering is chosen. In Wales, the Welsh Government says Article 4 directions "are most common in conservation areas", and the same check applies there.
A change from slate to a different covering is a question of weight and appearance, so building control and the planning team are asked before it is priced. Where the slates are kept and relaid, the question is simpler, and the survey says which case applies to your roof. Either way, the answer is written into the quote, so the approval route is settled before work begins and not discovered halfway through it.
A listed terrace adds consent of its own: section 7 of the Planning (Listed Buildings and Conservation Areas) Act 1990 in England, and sections 88 and 89 of the Historic Environment (Wales) Act 2023 in Wales.