Re-slating is not a cosmetic job. The slates can still be sound long after the battens, nails and underlay beneath them have given out, which is why a roof can need re-slating well before it needs new slate. The work is to take the covering off, put right the structure under it and lay the good slates back, with new ones where the old run short.
It runs in four stages, each with its own risks and its own checks: stripping, sorting, preparing the roof beneath, then relaying. Three decisions shape the price along the way, and each is settled with you before the slates are lifted. How many of the old slates go back? What new or reclaimed slate fills the gaps? Are the lead, ridge and verge renewed on the same visit? This guide takes the stages in that order, then turns to cost figures and to approval, with England and Wales in turn.
It belongs with our slate roofing guides.
Stripping: what comes off and what is recorded
Before a slate is lifted, the roof is photographed from ridge to eaves, so there is a record of what stood there. Scaffold goes up first. For a scaffold on the pavement or road, section 169 of the Highways Act 1980 applies, and we arrange the licence with our scaffolder. Scaffold sits inside the written quote, so access is never an extra.
Taking the ridge off first also shows how the top courses were fixed. Stripping then goes in sections and not across the whole roof at once, so only part of the house is uncovered at a time. Each section is taken from the ridge down: the ridge capping first, then the slates course by course. They are passed down, stacked on edge and kept apart from the waste. The old underlay and any battens that cannot be reused go in the skip, and the waste is taken away when the job is finished.
With the structure open, we record what the old covering was hiding:
- the rafters, for rot at the feet and for any sag along their length
- the wall plate and the tops of the walls where the eaves sit
- whether there was ever an underlay, and what state it was in
- the battens, for soft patches round the nail positions
- the lead at the chimneys, valleys and walls, and the chimney stacks themselves
You see these photographs before the relaying starts, with a note on each fault, because a rotten rafter foot is decided on in daylight and not once the slates are back on.
Sorting: the good, the cracked and the sick
Every slate that comes off is looked at. Sound slates are stacked for reuse. Cracked ones, and those that have started to flake or split along their layers, go for waste. Slates whose nail holes have worn through are set aside, because a slate that has lost its hold will slip again however well it is relaid. The sorted piles tell you in a few minutes how much of the roof is still serviceable.
| Pile | Condition | Outcome |
|---|---|---|
| Reuse | Whole, flat, holes intact | Relaid on new fixings |
| Waste | Cracked, flaking or split | Taken away |
| Cut down | Sound but damaged at one end | Trimmed for small spots |
| Short | Not enough sound ones to finish | Topped up with matched slate |
The piles are counted as well, so the quantity of new slate to order is known before the relaying starts. The top-up is where matching comes in. New Welsh slate, Spanish slate and reclaimed slate all differ in colour and thickness. HomeBuilding gives the lifespan of reclaimed Welsh slate as "50-80 years", against "100+ years" for new Welsh slate. SPAB advises putting claims of scarcity or long delivery to the quarries themselves, so if a slate is said to be unobtainable, the quarry is asked.
Welsh slate and stone roofs, SPAB notes, "are predominantly double-lapped", which matters when a replacement slate is cut or chosen. Our guide to natural or man-made slate compares the materials.
Battens, underlay and ventilation beneath
Battens are the cross-timbers that carry the slates. They are set out to the slate size and the headlap, the cover each course gives to the row two below it. Old battens are replaced where they are soft, split or nail-sick, and wherever the gauge for the new slate calls for different spacing. A slate is only as firmly held as the timber that takes its nail.
Beneath the battens goes the underlay. The choice between types is a ventilation question. With a high resistance (HR) underlay, which does not pass vapour, Marley asks for open eaves on a cold roof: 25 mm for pitches up to 15 degrees and 10 mm above that. Where a well-sealed ceiling sits beneath an air-permeable (LR) underlay, Marley accepts the 3 mm gap of ordinary eaves construction as enough, subject to third-party certification. A roof that has never had an underlay is a different case: the underside of the slates is open to the loft, and a new underlay changes how air moves through it.
Pitch sets what can be done above all this. Cupa reports that BS 5534:2014+A2:2018 gives 20 degrees as the lowest pitch for a natural slate roof, for moderate exposure, a 500 mm slate and a 115 mm overlap. For hooks the floor is 25 degrees, as our guide to nails or hooks for slates sets out.
Before any slate goes back, the structure below is therefore in order: sound timber, the right underlay, a clear route for air at the eaves and a gauge that matches the chosen slate.
Relaying, from the eaves up
Relaying works in the opposite direction to stripping. The slates are laid course by course from the eaves towards the ridge, and each course overlaps the one beneath. Fixings are nails or hooks according to the pitch and the specification. Every slate is held at its fixing and by the weight of the course over it.
The details around the edges are renewed in the same sequence, because they are the joints where weather gets in. If the pitch is low, the slates sit close to the limit, and the headlap is set to the maker's figure and not guessed. Every course is checked against a line as it goes down, so errors do not build up towards the ridge.
The sequence at the edges:
- The soakers and valley lead are checked or replaced as the slates reach them, as set out in lead details on a slate roof.
- Stepped flashings and back gutters at the chimneys are fitted into pointed joints.
- The verges are finished, with the slates fixed mechanically along the edge.
- The ridge goes on last. Marley says the 2015 amendments to BS 5534 ended mortar's role as the sole fixing, so a mechanical fixing is expected at ridge and hips.
Dry-fix ridge and verge systems are covered by BS 8612. Whichever system is chosen, the fittings have to suit the slate and the pitch.
Last comes the clear-up. Offcuts, broken nails and mortar crumbs are swept from the scaffold, the gutters and the ground, and the skip leaves with the waste. Before the scaffold comes down we photograph the finished roof from the angles used before the work, so the before and after pictures match.
What re-slating costs, from named guides
The published figures cover a wide spread, because roofs and slates vary. Which? (November 2025 survey, ex VAT) gives £7,000-£21,000 for a full roof replacement on a three-bed home. HomeBuilding (30 September 2025) has £10,000 to £15,000 for plain concrete tiles on a 65 m² semi, and writes that Welsh slate "might reach £18,000". MyJobQuote's slate page gives an average of around £7,800 for fitting a slate roof. The figures come from different surveys and different roofs, so they are read side by side and never averaged. Reclaimed slate can look cheaper on paper, but HomeBuilding's range for it, "50-80 years", sits below the "100+ years" it gives for new Welsh slate, and that trade is worth weighing.
For the covering alone, HomeBuilding's supply-only prices are £185 per m² for Welsh slate and £72 per m² for Spanish. Those are materials only, and they are never multiplied into a total.
What moves the price of a re-slate:
- how much of the old slate is sound enough to reuse, since every slate saved is one not bought
- whether the top-up is new, Spanish, Welsh or reclaimed
- how many battens, rafter feet or wall-plate lengths need replacing
- the underlay and ventilation chosen
- the lead, ridge and verge work done at the same visit
None of these is known until the roof has been inspected. What you receive afterwards is one total on paper, with VAT stated either in or out.
Approval and insulation in England and in Wales
Re-covering a roof is building work, and England and Wales treat it differently. This table sets the two sides together:
| Point | England | Wales |
|---|---|---|
| Approval | Planning Portal: none normally needed below 25 per cent of the building envelope and 50 per cent of the roof | Welsh Government: "In most situations, this work will need Building Regulations approval." |
| Insulation | AD L Table 4.3: threshold 0.35, improved 0.16 | AD L Table 11.1: 0.16, and not worse than 0.35 where 0.16 is not feasible |
| Limits | Para 4.13: payback of 15 years or less; generally not worse than 0.7 | Whole element above 50% (para 11.14); payback within 15 years |
| Next edition | AD L 2026 from 24 March 2027 | New Welsh AD L from 4 March 2027 |
Figures are in W/m²K. Both countries share a weight test. In England the Planning Portal says a covering adding "15 per cent or more" needs approval. In Wales, Approved Document A for Wales says a significant change in roof loading is one of "more than 15%". Roofs count as thermal elements under the Building Regulations, so a re-slate can raise the insulation question too. Both rules sit on top of the structural check, so a heavier slate is looked at by building control before the order is placed.
Before we start, we ask the council's building control team or a registered building control approver which route applies to the address.