Stand beside a chimney that rises through the slope of a roof and look up the hill. Every drop that falls on the slope above the stack runs down towards it, meets a wall, and has nowhere to go. A chimney on the ridge itself has no such problem, because the roof falls away on both sides. A chimney lower down the slope does, and the back gutter is the answer to it.
It is a lead-lined channel across the high side of the stack, laid on boards, with its ends tipped so the water leaves round both sides. Its high edge tucks beneath the tiles or slates above, and its rear edge climbs the face of the chimney into a chase. It is hidden by the very thing it protects, so it stays out of sight until it fails.
This guide takes the gutter apart in the order it is built, shows how it goes wrong and what a repair involves, and sets out the approvals that arrive when the stack itself is part of the job. The wider picture is on our lead roofing page.
What a back gutter has to do
A chimney stack on a pitched roof is a block that stands in the path of the water. Down each side of it, soakers and a stepped flashing carry the rain past. Across the lower face, an apron flashing is laid over the covering. On the uphill side, though, the water arrives in a sheet from the whole slope above, and a plain flashing against the brickwork would only hold it back and let it pool.
So the lead there is shaped as a gutter. It has a floor, a rear wall that climbs the brickwork, and a front edge that lies under the covering above. The floor is sloped from the middle to each end, which makes the water shed to the left and right, past the stack, and down the slope as if the chimney were not there.
The width of the stack sets the size of the job. A narrow single flue only has to part the water. A broad stack with several flues, or a wide chimney breast carried up through the roof, collects the run-off from a wider strip of slope and needs a longer, deeper gutter to cope.
When we survey a stack, we look for four things:
- where the stack sits on the slope, because that decides whether a back gutter is needed at all
- the width of the uphill face
- what covers the roof above it, slate, plain tile or stone tile
- the state of the brickwork or stone where the lead is chased in
How the pieces are built, in order
A back gutter is made of timber, lead and mortar, built up in a fixed sequence. When we fit or renew one, the work runs like this.
- The covering above the stack is lifted for a few courses, so the top of the gutter can run beneath it.
- Boards are laid between the rafters or battens to make a flat floor, with a slope built into it towards each side of the stack.
- A timber fillet, a small triangular strip, is fixed along the low edge where the floor meets the roof below, so the lead is not forced round a sharp angle.
- The lead is laid over boards and fillet in one piece, dressed up the face of the stack, and left long enough at the top to run under the covering.
- Its upper edge is turned into a chase cut in the brickwork or stone, wedged with lead wedges and pointed in mortar.
- The soakers and stepped flashings down each side are tied into its ends, and the covering is relaid over everything.
The point of the order is that each piece laps over the piece below it, like tiles, so the water can only travel downhill and outwards.
Royston Lead's table gives uses for flashings and for pitched valley gutters, and a back gutter is both a gutter and a flashing. It is the nearest guide. Royston lists Codes 4 to 6 for flashings and Codes 4 to 8 for pitched valley gutters. We choose within that range from the width of the gutter and the length of its laps. Code 3 is marked "Recommended for lead soakers only", so it does not go into a gutter.
The fall and the lap that keep it draining
Two details decide whether a back gutter keeps working: its fall and its lap. Getting either wrong shows up as the same sign, a patch of damp behind the stack, so they are easy to confuse from the loft.
The fall is the slope of the floor towards the two ends. Without it, rain, leaves and moss sit in the middle and the gutter becomes a shallow pond. With too little, the same thing happens more slowly. Lead is laid over boards that have been shaped to give the fall, so the work is in the carpentry as well as the metal. (BS 6229:2025, with its 1:80 minimum finished fall, covers flat roofs in flexible membranes, not lead; a back gutter is lead and the fall is set by the stack, not by that standard.)
The lap is the distance the gutter's high edge reaches beneath the covering, and the distance its sides reach beneath the soakers. A short lap lets wind-driven rain and meltwater run backwards past the top edge. A lap that is too short is hard to see from outside, because it is hidden under tiles that look perfect.
The comparison below shows the two states side by side.
| Detail | Sound | Needs work |
|---|---|---|
| Fall | Water drains to both sides | Leaf mould sits in the middle |
| Upper lap | Lead runs well under the covering | Edge sits close to the first course |
| Chase | Wedged and pointed tight | Pointing gone, lead lifting |
| Ends | Tied into the soakers | Gap at the corner of the stack |
Why back gutters fail
A back gutter fails as a slow chain, and the order of the chain matters because each failure helps the next.
The first link is debris. Leaves, moss and grit settle in the gutter, and the water behind them cannot get past. The second is standing water, which sits against the folds and the chase and works at any small weakness. The third is movement. Lead swells with warmth and shrinks with cold, and a long, tight piece cannot move freely, so it creases at the bend where the floor meets the rear wall. A crease that opens into a crack lets water through to the boards, and the boards below the lead start to rot.
The fourth link is the chase. When the wedges loosen or the pointing drops out, the top edge lifts and the rear wall of the gutter is no longer held to the stack. From then on, water tracks down the brickwork and in behind the lead.
Signs that this is going on are visible indoors and in the loft:
- a brown stain on the chimney breast upstairs, level with where the stack leaves the roof
- staining on rafters or boards just uphill of the stack in the loft
- moss or leaf litter showing at the edge of the covering above the stack
- daylight or a draught around the chimney in the loft
None of these proves a back gutter fault by itself. A stack can leak at its flaunching, its pots or its brickwork, so the survey tests each in turn. Our guide to step, apron and cover flashings covers the other lead pieces round the same stack.
Repairing or relining the gutter
The repair depends on what we find when the covering above the stack is lifted, and we photograph each stage so you can see it.
Sometimes the gutter is sound and only clogged. A clear-out, a check of the lead for splits and a refixed wedge may be all it needs. Where the lead is cracked at a fold, a patch is possible if the crack is short and the rest of the sheet is flat and clean. Where the lead has creased in several places, or the boards have gone soft, the gutter is stripped and relined. That means new boards with a proper fall, a fillet along the low edge, a new sheet of lead in the right code and fresh wedges and pointing in the chase.
One substitute turns up on old roofs: a cement fillet smeared in the angle behind the stack in place of lead. It is quick to apply and looks neat from a ladder. It depends entirely on the mortar, so when the mortar cracks nothing remains behind it. When we find one, we cut it out and build a lead gutter in its place.
Access matters here. The gutter is on the high side of the stack, so the work needs a stable way up. Scaffold on the public highway falls under section 169 of the Highways Act 1980, and we arrange the licence with our scaffolder. Our short answer on whether chimney leadwork needs scaffolding explains when a ladder or tower is enough. The price turns on the width of the stack, the covering above, the state of the boards and the access.
When the stack itself is part of the job
A back gutter is sometimes renewed because the chimney is being repaired, rebuilt or taken down, and more rules then apply. They differ between England and Wales, and they differ again for a shared stack.
- In England, the Planning Portal says that "Building regulations approval will always apply when removing chimney breasts as they are part of the building's structure".
- In Wales, the question goes to the council's building control or to a registered building control approver before the stack is touched.
- In England and in Wales, the Party Wall etc. Act 1996 reaches a stack that stands on a party wall. Its sections 2(2)(g) and 3(2)(a) give the owner doing the work at least 2 months' notice to serve before cutting a chimney breast away.
- Sections 5 and 10 provide for a surveyor when a neighbour objects, or when 14 days pass without an answer. Section 2(2)(j) also covers chasing a flashing into the next-door wall that a newly built wall abuts.
A listed house or one in a conservation area adds a second layer: the Planning (Listed Buildings and Conservation Areas) Act 1990 for England, the Historic Environment (Wales) Act 2023 for Wales. Whether work changes the character of the building is a call for the council, so a stack or its lead is raised with the council first.
Questions on a party wall go to a party wall surveyor, not to building control. A leaning or cracked stack belongs with our chimney work, and the new leadwork follows once the masonry is sound.