In brief
Water inside a metal-roofed building has two sources. One is a leak, where rain passes a lap, a fixing, a cut edge or a rooflight. The other is condensation, in which warm moist air from inside the building reaches the chilled steel and turns to water that drips off it. A leak shows during or after rain. Condensation shows on cold, still, damp days, even when it has not rained. The remedy for each is different.
Condensation: water that never came through the roof
Air indoors holds moisture from people, processes, washing down, heating and stored goods. A single sheet of steel on a cold day is far colder than the air beneath it. When that warm moist air touches the chilled metal, it cools, can hold less moisture, and gives the surplus up as water droplets. The droplets gather, run down the ribs of the sheet and fall as drips.
It is the same thing that happens on a window in winter. A roof can run with water on a morning that began dry, and the sheets above show nothing outside. Because bare metal is a cold surface in a building without a lining, moisture in the air can condense on it.
BS 5250 is the British Standard for controlling condensation in buildings. It carries the status "Current, Under Review", and Approved Document C of 2013 cites its 2002 edition, so the code is moving. A metal roof differs in build from a house roof, which is why the survey looks at what lies under the sheets, and how the building is used, before any advice is given. A cold store, a wash bay and a dry warehouse behave very differently under the same steel.
Leaks: rain getting past a lap or a fixing
A true leak is rain passing the roof. On a metal-clad building it enters at the weak points of the system, not in the middle of a sound sheet. We look in these places:
- the laps between sheets, where a sealant strip has perished or a sheet has lifted
- fixings with a failed washer or a rusted head
- cut edges where rust has gone right through
- rooflight junctions, kerbs and flashings
- gutters and valleys that have blocked and overflowed into the building
Our answers on rusting roof sheet fixings and cut-edge corrosion deal with two of them. A leak can follow the weather. If the drip begins soon after rain starts, and stops a while after it ends, the roof itself is the prime suspect. If it appears on dry mornings, think condensation first.
Water can travel inside a roof before it falls, along a purlin or a lining, and drip a long way from where it entered. So the spot under the stain is only the start of the search.
Telling the two apart, and what we do about each
The pattern of the drip gives most of the answer. This table sets out what we weigh on a survey:
| Clue | Points to a leak | Points to condensation |
|---|---|---|
| Timing | During or after rain | Cold, damp mornings, even when dry |
| Pattern | A few spots below a lap or fixing | A wide sprinkle across many bays |
| Stains on the sheets | Rust tracks from one point | Even dampness on the whole underside |
A leak is fixed at its source: washers, laps, flashings, edges or gutters. Condensation is handled by taking out the cause, so that warm moist air has less chance to reach cold metal. That may mean ventilation, a lining or insulation behind the sheet, or changing the way a process room is used, and the survey says which fits the building.
A roof can have both, and fixing one then shows the other. Our guide to finding leaks on large roofs describes how we trace a path. Any climb is made from a tower or a boarded route, since a damp sheet is slick.
Changing the roof: approvals, England against Wales
Adding insulation or a new covering to cure a drip brings in the Building Regulations. The thermal figures for a roof are set separately in each country:
- In England, Approved Document L (Table 4.3) sets a renovation threshold of 0.35 and an improved figure of 0.16.
- In Wales, Table 11.1 of the Welsh Approved Document L asks for 0.16, and not worse than 0.35 where 0.16 is not feasible.
- In England, the Planning Portal, writing about houses, reads that a Building Regulations application is not normally needed where "Less than 25 per cent of the total 'building envelope'" and "Less than 50 per cent of the roof" is affected.
- In Wales, the Welsh Government says that in most situations re-roofing needs Building Regulations approval.
Those tables are drafted for dwellings, so for a unit the first call is to building control. Our commercial roofing page explains how the work is quoted. After the survey you receive a single written total, scaffold included, and the site is cleared when we finish, with the waste taken away.