In brief
A roof sheet fixing is a screw or bolt with a sealing washer, driven through the sheet into the purlin below. It rusts when its own coating has worn or been scratched, when water and dirt sit around the head, when it was over-driven and crushed the washer, or when a fixing of one metal sits against a sheet or washer of another. The sheet may be sound. Replacing the fixings, with the right type and washer, can be the repair.
What a fixing does and where it is weakest
The sheets on an industrial roof are held down by fixings: self-drilling screws or bolts that pass through the sheet and bite into the purlin, the beam running across the building. Under each head sits a washer faced with a sealing material, which keeps rain out of the hole the screw has made. That hole is the weakest point in the system. Water that gets past a failed washer runs down the screw and into the steel below.
A fixing is coated, like the sheet, so that it resists rust. Weather, movement and damage wear that coating away. A head is also a small shelf, and dirt, moss and standing water gather round it. A roof that is wet for long periods puts every fixing under strain, particularly at the laps, where two sheets meet and the screw passes through both.
When we survey, we note the type of fixing, the state of its washer and whether the head is clean or stained. A line of orange heads along a lap is a pattern worth recording. Our commercial roofing page shows where a fixings survey sits in the wider work.
Five reasons a fixing rusts
A rusty head has more than one possible cause, and the repair differs for each. These are the ones we look for:
- a worn or scratched coating on the screw, so the bare steel is exposed to every shower
- a perished or crushed washer, where the sealing face no longer closes the hole
- an over-driven screw, which dishes the washer and traps water in the dish
- unlike metals in contact, such as a fixing of one metal in a sheet of another, which the survey checks wherever the two meet wet
- the wrong grade of fixing for the building, such as one chosen for a dry shed and fitted to a damp process hall
Condensation under the roof can soak the tips of the screws from below, as well, so a fixing can corrode from the inside out. Where several causes are present, the survey records each, with photographs of the heads before anything is touched.
Not every orange stain comes from the fixing. Rust that begins at a sheared sheet edge is a different fault, which our answer on cut-edge corrosion deals with.
Replacing fixings, or the sheet
The aim of a fixing repair is to take out the failing screw and put back one that will last in its place, with a washer that seals. A few points matter:
- the new fixing matches the sheet and the purlin, in metal and in grade, so the same fault does not return
- the old hole is checked, because an enlarged or rusted hole will not hold a screw of the same size
- the washer is seated flat and driven only far enough to close, not crush
- the sheet around the hole is cleaned and any lost coating restored
If the sheet itself has thinned or holed beside the fixing, replacing the fixing alone will not cure it, and the sheet comes off. If rust is widespread, with fixings failing along every lap, the better buy may be a wider repair or an overlay, and the photographs show why. Our page on repairing, overcladding or replacing a metal roof sets out those choices. Because fixing work is done from the roof, access is planned first, as the answer on who can go on an industrial roof explains.
Rules and the paperwork, England and Wales
Swapping a handful of fixings is maintenance. A wider job to re-fix or re-cover a roof meets the rules, and the answer depends on the country:
- In England, the Planning Portal, writing about houses, explains that no application is normally required where "Less than 25 per cent of the total 'building envelope'" and "Less than 50 per cent of the roof" is affected.
- In Wales, the Welsh Government says of re-roofing: "In most situations, this work will need Building Regulations approval."
For a unit, ask building control which test applies. CDM 2015 regulation 15(5) makes a plan for the construction phase a duty of the lone contractor, and that duty is identical for a Hereford unit and a Monmouthshire one.
If the roof is asbestos cement, HSE says "AC roofs are always fragile", and a building built or refurbished before 2000 is to be treated as containing asbestos until shown otherwise. Fixings in such sheets are not undone casually, because breaking a sheet changes the HSE band of the work. The scaffold is part of the single written total that comes after the survey.