01432 610152 Get a quote Call 01432 610152

Welsh chimney removal

Can I remove a chimney in Wales without planning?

In Wales, a chimney cannot be removed under permitted development if the house stands in a conservation area, a National Park or a National Landscape.

In brief

Not always. Under the Welsh Class C, removing a chimney is excluded from permitted development on article 1(5) land, meaning a conservation area, a National Park or a National Landscape (AONB), and within a World Heritage Site. Elsewhere the removal can fall within Class C, subject to its conditions. A listed house also needs listed building consent, and the Building Regulations are a separate step.

What the Welsh Class C leaves out

Wales still relies on the 1995 General Permitted Development Order, amended for Welsh use. Class C reads "Any other alteration to the roof of a dwellinghouse". Paragraph C.1(c) then lists what Class C does not cover, and two entries matter here: "(i)the installation, alteration or replacement of a chimney" and "(vii)the removal of a chimney from a dwellinghouse on article 1(5) land or within a World Heritage Site".

The Welsh Government's technical guidance defines article 1(5) land as "land in Wales within a National Park, an area of outstanding natural beauty and an area designated as a conservation area". So a house in a Welsh conservation area, in the Bannau Brycheiniog National Park or in the Wye Valley National Landscape on the Welsh bank cannot use Class C to lose its chimney.

Beyond that land, taking a chimney away can fall within the general wording of Class C, which is why the answer depends on the address. Alteration or replacement is a different matter: entry (i) stands whatever the land. A house in the National Park should ask the National Park Authority, and anywhere else the question goes to the council.

Where the line falls for your address

The first question is whether the house stands on article 1(5) land. The table sorts the cases that come up, and the council can confirm which row applies to your address.

Chimney removal under the Welsh Class C
Where the house standsRemoval under Class C
Conservation areaExcluded by C.1(c)(vii)
Bannau Brycheiniog National ParkExcluded by C.1(c)(vii)
National Landscape (AONB)Excluded by C.1(c)(vii)
Elsewhere, house not listedCan fall within Class C, with its conditions

An Article 4 direction can also withdraw rights that Class C would otherwise give. The Welsh Government notes that these are most common in conservation areas, so check whether an Article 4 direction applies before you commit to a date. Ask the council which row your street falls in, because a boundary can run down the middle of a lane.

When planning permission is needed, the application goes to the council, and a house within the Park's boundary is the Park Authority's concern instead. Get the decision on paper and store it with your roof papers, since a buyer's solicitor may ask to see it later.

The roof you are left with, and listed houses

Taking down a stack leaves a hole in the roof that has to be closed. Condition C.2(a) of the Welsh Class C asks that "the appearance of the materials used in each element of any exterior work must so far as practicable match the appearance of the materials used in the equivalent element of the existing dwellinghouse". For us that means the slate, tile or stone infill is matched to the slope around it, and the finished patch is photographed for you.

A listed house follows a different route. Under the Historic Environment (Wales) Act 2023, section 88, works that alter the special interest of a listed building must be authorised by listed building consent under section 89. The Welsh Class C has no listed-building exclusion, so the rights stay and the consent is needed as well.

Bats and nesting birds also come into it. Under section 1 of the Wildlife and Countryside Act 1981, it is an offence to intentionally take a wild bird's nest from a stack, or to harm it, while the nest is being built or used. Natural Resources Wales licenses bat work, and the Habitats Regulations catch damage to a roost whether or not harm was meant. If a pot or cavity is occupied, work stops and advice is taken.

Building Regulations, party walls and the order of work

Planning is not the only control. The Welsh Government's roof guidance says approval is needed if you "carry out structural alterations", and a chimney breast with its stack can carry load from the floors and roof. Ask the council's building control service or a registered building control approver before you start. Wales has had a new building control regime since 1 July 2026, so confirm which route applies on the day you apply.

Should the breast back onto the neighbour's house, the Party Wall etc. Act 1996 applies in Wales as it does in England. Cutting away a projecting breast falls under section 2(2)(g), with a notice served at least 2 months ahead, which the notice page sets out.

The order we suggest is:

  1. confirm whether the house is on article 1(5) land or listed
  2. settle planning with the council or the Park Authority
  3. settle Building Regulations and any party wall notice
  4. book the roof work, with the infill priced inside one written total

The wider chimney repairs hub explains the rest, and the roof after a stack comes down covers the finish.

Related questions

Is repointing a chimney in Wales permitted development?

Repointing mends an existing stack and does not replace it. Entry C.1(c)(i) of the Welsh Class C covers the installation, alteration or replacement of a chimney, which puts a rebuild in another category from a repair. A listed house needs consent for either if the character is affected.

Do I need planning permission to remove a chimney in a Welsh National Park?

Yes, because C.1(c)(vii) takes removal of a chimney on article 1(5) land out of Class C, and a National Park is article 1(5) land. Apply through the planning authority for the Park, and check with the National Park Authority before you plan a date.

Get your free roof quote

Tell us about the roof and we will arrange a survey.

10-year workmanship guarantee, in writing