The chimney breast is the block of masonry that projects into a room and carries the flues up through the house. It looks like a fitting, and it behaves like a wall. The floors may bear on it, the chimney above the roof may rest on it, and if the house is joined to another, it may be built into the wall you share. Removing one means thinking about what it holds up, and about who else has an interest in it.
Three sets of rules can apply, and they apply to different things. Building Regulations ask if the structure will stand and stay sound. The Party Wall etc. Act 1996 looks after your neighbour's position. Planning and listed building law deal with the outward appearance and the character of the building. A breast that is in a detached house with no listing needs the first; a breast in a listed terrace may need all three.
The sections below explain why the breast matters structurally, the approval route that applies in England and in Wales, the party wall notice and its timing, the planning and listing points, what happens to the stack above, and what sets the price. Our chimney repairs page covers the roof end of the same job.
Why a breast is structure, not decoration
A chimney breast carries the flues from the fireplace up through the house and out above the roof. Inside the rooms it looks like a stub of wall, but the brickwork can be bonded into the walls on either side, and the stack above rests on it. Take away the breast and you take away the support for whatever stands on it.
That is why the work is not simply a matter of knocking out masonry. Three questions need answers before anyone picks up a hammer.
- What does the breast carry? In an upstairs room it may hold up the stack and the breast above, and in a ground-floor room it may carry the first-floor breast too.
- Is it bonded into the party wall? If the breast is tied into a wall that next door relies on too, their rooms are affected.
- What happens to the stack above the roof? If the breast is removed, the stack may be taken down as well, or it may be left standing and supported by a new structure in the room below.
Removing only the lower breast and leaving the stack above is possible, but the weight of the stack then has to be carried by something. That support is designed by someone qualified to do it, and it is checked by building control. It is not a job for a quick guess, because a stack sitting on nothing is a hazard to the people below and to the neighbours.
Our side is the roof end of the job, meaning the shaft, pots and lead. A builder or structural engineer deals with the breast inside. A good job has both ends planned together.
Building Regulations: England and Wales
Building Regulations approval is the main gate. The advice reads differently in England and in Wales, because the published sources differ, and the two bullets below keep to what each one says.
- In England, the Planning Portal says: "Building regulations approval will always apply when removing chimney breasts as they are part of the building's structure."
- In Wales, put the question to the council's building control service or to a registered building control approver before a breast comes out.
On either side of the border, the approval is for the structural work and for the way the stack above is supported. You make the application, or your builder does, and building control inspects as the work goes on. Since the Building Regulations are about safety, an approver will want drawings and calculations for the support, and will inspect the new support and the opening before they are closed up and plastered. Keep the paperwork that results, because it is the record that the structure was checked.
The council's building control service is one route. A registered building control approver can take the application in its place, in England and in Wales, so you choose which to ask. Our own part is the roof end, and the application for the breast is made by you or your builder.
A breast removed as part of a loft conversion or an extension is covered by the application for that larger job.
The Party Wall etc. Act and your neighbour
When the breast sits in a wall that belongs jointly to you and next door, the Party Wall etc. Act 1996 comes into play, in England and Wales alike. The building owner, meaning the person having the work done, serves the notice. Neither the builder nor the roofer does.
| Step | Rule |
|---|---|
| Cutting away a projecting breast, jamb or flue | Section 2(2)(g) gives the right |
| Notice before the work begins | At least two months, section 3(2)(a) |
| Neighbour's written consent | Section 3(3)(a): the work can go ahead on it |
| No reply | Dissent after 14 days, section 5 |
| Dispute | A surveyor appointed under section 10 |
GOV.UK warns: "You cannot assume that no response means they agree to the works." So silence does not help you. Surveyors enter only on dissent, or after 14 days with no reply.
The Act does not stand in for Building Regulations, nor they for the Act. On the notice itself, a party wall surveyor can advise you; building control cannot. If the breast belongs wholly to your house and does not touch the shared wall, the Act may not be engaged, and a surveyor can confirm which case you are in.
Our guides on chimneys on a party wall and on the notice to cut away a shared chimney breast go through the notice in more detail. Because the minimum is two months, the notice is the first step to take, before the builder and the roofer are booked.
Planning, listing and protected areas
Taking out a breast inside a room need not be a planning matter, because it changes nothing on the outside. The outside enters the picture when the stack above the roof is taken down or altered, because the Orders treat chimneys separately from the rest of the roof.
- In England, Class C of the 2015 Order covers other alterations to a roof, but its condition C.1(d)(i) excludes work that consists of or includes "the installation, alteration or replacement of a chimney, flue or soil and vent pipe".
- In Wales, Class C.1(c)(i) of the 1995 Order excludes "the installation, alteration or replacement of a chimney", and C.1(c)(vii) excludes "the removal of a chimney from a dwellinghouse on article 1(5) land or within a World Heritage Site".
In Wales, article 1(5) land includes a National Park, an area of outstanding natural beauty and a conservation area. A house in the Bannau Brycheiniog National Park or a Welsh conservation area is therefore outside Class C for taking a stack down, and the council can say whether planning permission is needed. In England, ask the council whether taking a stack down counts as an alteration.
A listed house adds a further consent, and the law differs by country.
- In England, listed building consent comes under section 7 of the Planning (Listed Buildings and Conservation Areas) Act 1990.
- In Wales, the Historic Environment (Wales) Act 2023 applies: section 88 on authorising works and section 89 on listed building consent.
Flats do not carry householder permitted development rights under the 2015 Order, article 2, so a flat owner should ask the council about any change to a shared stack.
What happens to the stack above the roof
When a breast comes out, one of two things happens to the stack above, and the roofer is involved either way.
- The stack comes down. The pots and shaft are taken down to the roof or to just above it, the opening in the roof is closed, and the roof is made good with new covering, battens and lead where needed.
- The stack stays. The stack is supported on a new structure in the room below, and the roofer checks the pots, the collar and the flashings, and renews what has failed.
Taking the stack down suits a flue nobody uses and a stack in poor repair. The rest of the job is at roof level.
- Dismantling: pots off, then the shaft course by course, from a safe platform.
- Capping: any flue left open is capped, and where a flue stays in use, it is left with its pot.
- Roof repair: the slope is made good with matching tiles or slates, and the lead tray and flashings are removed.
- Ventilation: a flue left in place below the roof is generally ventilated, so it is not sealed airtight.
Where tiles or slates are available, we match them to the roof. On a stone-tiled roof, SPAB advises that "Claims of unavailability or long delivery times should always be checked with the quarries."
Scaffold is needed for the work, and on the street it needs a licence under section 169 of the Highways Act 1980. We arrange the licence with our scaffolder.
What sets the price
The price of taking out a breast depends on several things, and no two houses are the same. Once surveyed, you get one written total, and these are the things that move it.
- How many breasts come out, and on how many floors.
- Whether the stack above is taken down or supported.
- The support needed, which depends on what the breast was carrying.
- Access, scaffold and the licence if it stands on the street.
- The roof repair after the stack is gone.
- Making good the walls, floors and ceilings, and the decoration.
- Fees for building control and, if it applies, the party wall surveyor.
For context, MyJobQuote (page dated 3 November 2026) says "The average cost of removing a chimney breast is around £2,500", with a range "between £1,200 and £3,500", and "the average price for removing the entire chimney stack with the breast is around £3,000 to £3,500". These are third-party typical UK figures, not ours, and a stack on a tall house with difficult access is a different job from a ground-floor breast in a bungalow.
The way to keep the cost down is to make the decisions in order: settle what is being removed, serve the party wall notice if it applies, apply for Building Regulations approval, and only then book the trades. Doing it the other way round, with the breast out first and the paperwork afterwards, is the expensive route.
If you are thinking about breast removal, a survey of the stack and the roof is a good first step. Photographs from your own roof come with the survey, and the written total follows.