Insulation figures

What insulation level is needed after foam removal?

With the foam gone, the roof is insulated again to a U-value set in Approved Document L. England and Wales publish separate documents, and their figures differ.

Short answer

For a renovated roof, aim for 0.16 W/(m²·K) in both countries. In England, Approved Document L 2021 Table 4.3 gives 0.35 as the threshold and 0.16 as the improved figure, with a relaxation in para 4.13. In Wales, Table 11.1 gives 0.16, and not worse than 0.35 where 0.16 is not feasible. Lower numbers mean better insulation.

Reading a U-value

Heat loss through a building element is measured as a U-value, with the unit W/(m²·K). The figure describes the whole build-up of the roof, not one layer, so 0.16 is what the finished roof achieves with insulation, rafters, boards and lining taken together. A smaller number means less heat escapes through the roof.

The Building Regulations 2010 define a thermal element as "a wall, floor or roof", leaving out windows, doors, roof windows and rooflights, so your roof is the element in question in both countries. Windows set into the roof have their own figures, and they are the same on both sides: a roof window needs 1.4 or WER Band B, while a rooflight is held to 2.2.

Two further points save confusion. A figure belongs to a particular table, so the same roof can face different numbers depending on whether the work counts as new or renovated. And figures change with each edition, so the date of the document matters as much as the number itself.

Foam does not alter any of this. What it changes is the survey, because the roof has to be looked at afresh once the foam is out, and the build-up that results is what building control assesses.

England: Approved Document L 2021 until March 2027

The English document now in force is Approved Document L 2021, with 2023 amendments, which has applied since 15 June 2022. Table 4.2 applies to new elements in an existing dwelling and gives 0.15 for a roof. Table 4.3 applies to existing elements, including renovated ones and loft conversions, and gives a threshold of 0.35 with an improved figure of 0.16.

Para 4.13 allows a relaxation. Where the improved figure is impractical, or would take longer than 15 years to repay its cost, the roof is improved as far as a 15-year simple payback allows. The document then expects a roof so treated to come in at 0.7 or better, as a general rule.

Approved Document L 2026 takes effect on 24 March 2027, with the same tables renumbered 3.2 for new elements and 3.3 for existing ones. Until then Tables 4.2 and 4.3 apply, and the newer edition does not yet.

Whether your particular job counts as renovating the roof element is for building control to confirm. Ask the council's building control team or a registered building control approver before the insulation is chosen.

Wales: its own document, its own figures

Wales publishes its own Approved Document L, issued for use there. The 2022 edition, with 2024 amendments, took effect on 23 November 2022, and a new one follows on 4 March 2027.

Table 4.1 gives 0.13 as the worst acceptable figure when a roof element is newly built in an existing home. That is a table for new elements, so it is not the one to reach for when an existing roof is only recovered or re-insulated. For retained fabric the guide is Table 11.1, which sets column (a) at 0.16 and column (b) at 0.35.

The Welsh rules work differently from England's. Para 11.14 improves the whole element if more than 50% of its surface is being renovated. Paras 11.20 and 11.21 cover the case where 0.16 would be uneconomic, impractical or technically out of reach: the roof is then taken to the best level that can be managed, which generally should be no worse than 0.35. The economic test is repayment within 15 years.

Local authority building control in Wales is regulated by the Welsh Ministers, and a Welsh address can start with the council's team or a registered approver.

Both nations in one table, and our part

Roof insulation figures, England and Wales
PointEnglandWales
New roof element0.15 (Table 4.2)0.13 (Table 4.1)
Renovated roof0.35 threshold, 0.16 improved (Table 4.3)0.16, not worse than 0.35 (Table 11.1)
Roof window1.4 or WER Band B1.4 or WER Band B
Next edition24 March 20274 March 2027

On a foam job we measure the rafter depth first, because the depth decides how much insulation fits between the timbers and whether a layer is needed above or below. We then settle which figure fits your address, England or Wales, and ask building control. The answer goes into the written total price, so there is no extra line for insulation to surprise you later. Photographs of the build-up go into your records too, with the depth of insulation noted in each bay, so a later buyer's surveyor or the building control officer can see what was fitted and where.

Our answers on foam or mineral wool between the rafters and loft ventilation after foam removal cover the choices that go with it, and our spray foam removal page covers the job as a whole.

Related questions

Does the old foam count towards the new figure?

Foam that has been removed counts for nothing, because the roof is assessed as it will stand after the new work. If some foam stays in one section, it forms part of that build-up. The council's building control team or a registered approver decides how the layers are judged, and we record each one so they have what they need.

Do the 2027 editions change what I should fit now?

In England, Approved Document L 2026 takes effect on 24 March 2027, with the tables renumbered and the roof values for new elements unchanged at 0.15. Wales's successor takes effect on 4 March 2027. Which edition a job follows turns on its dates, so ask building control which one your work falls under.