How long it takes

How long does taking spray foam out of a roof take?

The roof sets the length of a foam removal job: its area, the foam type, access and what lies underneath. Here is what stretches it and what we plan around.

Short answer

There is no fixed length, because the roof decides it. A small slope of soft open-cell foam is a different task from a whole roof of closed-cell foam stuck to underlay and tiles, and any repair found underneath adds to it. When the survey has been carried out, the single written price arrives with the stages listed and the time we expect for your own roof, so nothing is left as a guess.

What sets the length of the job

Published prices for foam removal are given per square metre, and that already tells you something: area is the first driver of time as well as of money. MyJobQuote averages £40 per m² for removal, and puts a 3-bed detached property at around £3,200 in total. Past the area, six things stretch or shorten a job:

  • the foam type, since closed-cell bonds more rigidly to the rafters and takes longer to clear, as Checkatrade notes
  • how much of it is bonded to the underlay or the backs of the tiles
  • access through the hatch, and whether the joists are boarded
  • what the timber turns out to look like once it is clear
  • whether repairs are done in the same visit
  • whether new insulation goes in straight after

The first four cannot be judged from the street. The survey looks at the foam surface from the hatch, the cut edges around pipes and the state of the covering outside, and from those we put the stages in order. If you are not sure which kind you have, our guide to which spray foam you have will help you check before the survey.

The stages, and where time goes

Removal runs in a fixed order, and some stages grow more than others. The table shows where a long job loses its hours.

The stages of removal and what stretches them
StageWhat happensWhat stretches it
Preparing the loftClearing, sheeting, boarding, lampsA crowded or unboarded loft
Lifting the foamBay by bay, bagged as we goClosed-cell foam, or foam on underlay
Reading the timberProbing and photographingDamp or soft areas
Making goodRepairs, then new insulationAnything the foam was hiding

Taking the foam off may not be the part that surprises people. The surprise comes at the third stage, when the rafters can be seen again after years under the foam. A clear timber adds nothing, but a damaged one adds repair work, so we photograph it, show you the pictures and settle the way forward together before work continues. That conversation costs a little time, and it keeps you in charge of what happens next. Our guide to how spray foam is removed takes each stage in turn.

Scaffold notice and the lead time before a start

Some of the waiting happens before anyone climbs a ladder. When the work needs scaffold on the road or pavement, a licence under the Highways Act 1980 s169 comes first, and we arrange the licence with our scaffolder. The councils set their own minimum notice, and each states it differently:

  • In England, Herefordshire Council asks for applications at least 10 days before the scaffold needs to be placed.
  • In England, Gloucestershire County Council asks for at least twelve calendar days.
  • In England, Shropshire Council wants applications ten working days (Saturdays excluded) ahead of the date.
  • In Wales, Monmouthshire County Council asks for at least 5 working days.

Where the scaffold stands on private ground, none of this applies. Either way, scaffold is part of the one written price, and the same document names the start we expect once any licence is in hand. A date given before the survey would be a guess, and the survey is what shows whether a licence is needed in the first place. Where the notice period is the longest, it is sensible to book the survey early so the licence can be applied for while you decide.

Starting sooner, and your cooling-off days

Under the Consumer Contracts Regulations 2013, the cancellation period for a service ends 14 days after the contract is entered into, and an agreement reached at your own house after our survey is covered. That rule runs alike across the border, in England and in Wales. A start inside the fortnight needs your own written request, by email or letter. Calling someone in for an urgent repair is treated differently, and that visit carries no cancellation right.

Nothing in this stops you taking time. A written total that stands for the period you need lets you read it twice, and you can ask for any stage to be explained before you sign.

The same regulations are why a quote does not rush you. You can take the written total home, compare it with a roofer's price from anyone else, and ask for the stages to be explained. Citizens Advice runs the consumer helpline on 0808 223 1133, and 0808 223 1144 for a Welsh-speaking adviser.

When the foam has gone, fresh insulation follows, and the rules for it differ either side of the border. Our answer on the insulation level after foam removal sets them out, and our spray foam removal page shows the whole job.

Related questions

Does wet weather delay foam removal?

Work in the loft carries on in rain. Lifting tiles from outside, which is sometimes needed where foam is bonded to their backs, waits for a dry spell, because an open slope has to be covered again before we leave. If the weather will move a day, we tell you what changes and when.

Is the time in the quote a promise?

It is our expectation for your roof, based on the survey, and not a fixed number of hours. What the lift shows can move it either way. If a bay turns out harder than it looked, or a repair appears, we photograph the cause and tell you what it means for the schedule before carrying on.