In brief
Yes, on the right day. A flat roof covering needs a dry, sound deck beneath it, because moisture or frost sealed under a membrane stays trapped there. So winter work follows the forecast and the manufacturer's installation guide for the system chosen, and a morning that is too wet or too cold is moved, not forced. The roof is opened only as far as it can be closed again before dark.
What the covering needs from the deck underneath
A flat roof is built in layers: the structural deck (timber boards or a concrete slab), any insulation, then the waterproof covering on top. The covering depends on a sound surface below it. Laid over a deck that is damp, or carrying a skin of frost, it seals that moisture in, where it can stain the ceiling below or soften the boards.
Each system has its own limits. Torch-on felt is bonded with a flame, EPDM rubber is stuck down with adhesive, and GRP (glass-reinforced plastic, sold as fibreglass) is a resin that cures on site. Every manufacturer publishes the conditions its product can be laid in. The installation guide for the system picked for your roof sets the limit for your job, not a date in the calendar.
That is why a winter booking is a window and not a fixed day. If the morning is wet or frosted, the work moves to the next dry one. The page on torch-on felt roofs today explains how that covering is laid, and the flat roofing hub covers the other options.
How a winter working day is run
Winter days are short, so the job is planned around what can be finished and sealed before the light goes. Before the first sheet comes up we check:
- that the deck is dry to the touch and firm underfoot
- that no frost sits on the deck or on the upturns round its perimeter that rise against a wall
- that the forecast for the afternoon and evening is dry
- that the area stripped matches the area that can be re-covered in that working day
- that sheeting is on site in case rain arrives early
Stripping the entire roof in the morning and hoping for a dry night is a plan we avoid. The roof is opened in sections, and each one is made watertight before the next is begun. If the old layer is stripped and the new one cannot be laid, that section is covered over and the job waits for another dry morning.
A leak in winter is a separate question. A roof already letting water in may need a temporary repair first, and the choice between mending and renewing is set out on the page about patching or replacing a flat roof.
Approval and insulation when the covering is replaced
For England, the Planning Portal sets a test: a re-covering normally needs no application when less than 25 per cent of the building envelope and less than 50 per cent of the roof are involved. Extra weight is its own trigger, and the Portal sets it at a rise of 15 per cent or more in the weight of the covering. Under Approved Document L in England, re-covering a flat roof counts as renovation, and Table 4.3 gives a threshold of 0.35 and an improved figure of 0.16 W/m²K for the existing roof.
For Wales, the Welsh Government's view is that re-roofing will in most situations need Building Regulations approval. Its flat roof guidance adds that some repairs need no application, while replacing a roof whose insulation is built in can mean upgrading the thermal element. Table 11.1 of the Welsh Approved Document L asks for 0.16 W/m²K, with 0.35 as the limit where 0.16 is not feasible.
Either side of the border, we check with the council's building control service or a registered building control approver before a start date is fixed. A winter slot is worth little if the approval is still to come.
Booking a winter start and the cooling-off period
After the survey you get one total, in writing. In winter it is worth reading for what it says about the weather, so ask for these points to be set down:
- the covering chosen, and the conditions in the manufacturer's guide
- what happens to the booked day if the deck is wet or frosted
- whether VAT is added, and whether the total covers scaffold
- who handles any Building Regulations application
Sign at home after the survey and the Consumer Contracts Regulations 2013 give you 14 days to change your mind, in England and Wales both. A start inside that period happens only if you ask for it in writing. A repair visit you invited because of an urgent leak carries no such right. The Citizens Advice consumer helpline is 0808 223 1133, or 0808 223 1144 for a Welsh-speaking adviser.
If a flat roof is old but dry, the settled days at the far end of winter cost nothing to wait for. If it is letting water in now, a temporary repair comes first and the new covering follows when the deck is fit to take it.