In brief
That lead is a flashing. A conservatory and the house behind it move by different amounts, so the joint between them cannot be a rigid seal. A strip of sheet lead is tucked into a groove in the masonry known as a chase, then lapped over the roof edge. Lead bends to shape, stays flexible and sheds water. Royston Lead lists Codes 4 and 5 for flashings.
What the lead is doing at the house wall
Think of the house wall as a big, flat catchment. Rain lands on it, runs down, and arrives at the back edge of the conservatory roof, where there are two routes: over the roof, or behind it. The flashing exists to force the first route.
One edge of the lead is turned into the chase, which is a groove cut along a mortar joint in the brickwork or stonework. It is wedged tight there and pointed up so that it cannot slide out. The other edge lies over the roof, resting on the cap above the first glazing bar or on the edge of the sheets. Since the lead overlaps the roof rather than tucking under it, falling water meets metal first and drops clear of the wall.
Lead gets the job because a roofer can hammer and fold it into corners and bay returns on site, and because it never sets rigid the way a gunned-on sealant does. When a warm week and a cold night shift the roof against the wall, the metal flexes with the joint. A bead of sealant by itself cannot do that, and in time it parts from the brick.
Which lead codes are listed for flashings
Lead sheet is graded by a code number, and each number is a thickness. Royston Lead's cast-lead brochure sets out which codes suit which job, using its own lettering for the jobs. Soakers are its group A and flashings its group B.
| Code | Thickness | Soakers | Flashings |
|---|---|---|---|
| Code 3 | 1.32 mm | Listed | Not listed |
| Code 4 | 1.80 mm | Listed | Listed |
| Code 5 | 2.24 mm | Not listed | Listed |
Soakers are the little folded lead pieces that sit between tiles at a roof edge, which is a separate job from a wall flashing. Royston marks Code 3 "recommended for lead soakers only", so that grade stays off a long wall run. Both Code 4 and Code 5 are listed against flashings. At the wall we weigh how long the run is and how tight the folds are, then photograph the new lead against the brickwork before the roof edge is closed over it. That photograph goes to you, so you can see what is now hidden behind the cap.
Why the lead lets water in
The metal itself may not be the part that gives up. MyJobQuote writes that, installed correctly, lead flashing can last for over 80 years, a hedged statement and not a promise, so when water arrives the cause can be what is holding the lead in place.
These are the faults we look for along this joint:
- the pointing in the chase has dropped out, letting the lead lift or creep
- a fold has split where it was bent too sharply or has flexed many times
- the lower edge no longer reaches over the roof cap, so water slips under it
- a thick smear of sealant covers a gap where a flashing should be
- the wall higher up is soaked by a faulty gutter or downpipe, giving a stain that looks like a flashing leak
The guide to leaks at the conservatory house wall follows that last case through. We examine the brickwork above the lead before blaming the metal, since a new flashing cannot stop water that arrives from higher up the wall. A hose test from the top down, one section at a time, can separate the two causes when the stain alone does not.
Renewing the lead: cost and rules
For chimney flashings, MyJobQuote's page of September 2026 gives a lead patch repair at around £200 and a full replacement at around £570. A conservatory wall flashing is a different length of lead, so treat those as a sense of scale, not a quote for your roof. Our price is a single figure in writing, set once the survey is done.
The flashing is normally renewed as part of wider conservatory roof work. Building rules are split by the border, so each side is set out here:
- In England, the Planning Portal wants a replacement conservatory roof to meet building regulations, and Approved Document C refers to BS 6915 for lead.
- In Wales, the Welsh building regulations apply, so ask the council's building control service or a registered building control approver before the roof edge is opened up.
Where the flashing meets the guttering at the end of the wall, read gutters and lead on conservatories.
Either way, the joint is photographed open, so the condition of the chase and the old lead is on record before anything is closed, and the written quote reflects what the open joint showed.