A conservatory was designed for a light roof. Glass and polycarbonate sheet are both light, and the frame, the dwarf walls beneath it and the foundations below them were sized for that load. A tiled or insulated solid roof is a different structure. It has timber or steel in the roof itself, boards, insulation, battens and a covering, and all of that sits on the frame.
So the question is not whether a solid roof can be fitted. It is whether this frame and these walls can carry it, and the answer comes from a survey and, where the figures are tight, from a structural calculation. A yes over the phone from a photograph would be a guess.
The sections below set out what we look at, what the Building Regulations ask on each side of the border, and what the alternatives are if the answer is no. For the wider choice of roofs, see our conservatory roofs page.
Why a solid roof asks more of the structure
Weight is the first difference. A glazed or polycarbonate roof is a light skin on a light frame. A solid roof is a built-up roof, with its own structure, and the load travels down through the frame into the dwarf walls and then the foundations. If any part of that chain was only just adequate for a light roof, the extra weight shows up there first.
The load does not only act downward. A heavier roof pushes outward on the frame at the eaves, and it puts a concentrated load onto the point where the conservatory joins the house. For those reasons, the frame is checked as a whole, not post by post.
The weight rule sits in the Building Regulations. In England, the Planning Portal sets its trigger at a covering that adds weight "by 15 per cent or more", and AD A, in its own words, calls it a significant change when loading is increased "by more than 15%". The Welsh AD A carries the same words: "more than 15%". A tiled build-up may pass that point, but the weight of the roof being replaced is the starting figure, not a guess.
The 15 per cent test triggers a structural check and approval. It belongs to the Building Regulations, never to planning. It does not tell you the structure is sound. For that, the load has to be worked out. Wind and snow add to the roof's own weight, and a flat or low-pitched solid roof holds snow longer than a steep one. Those loads are part of what the engineer's figures cover, which is why we do not quote a safe weight from the survey alone.
What the survey checks in the frame, walls and foundations
We survey the conservatory from the outside in, and from the foundations up. The checklist is short, and each item is photographed.
- The frame: its material, its section sizes and whether any post has moved, bowed or rotted.
- The dwarf walls: their construction, whether they are bonded or only stacked, and any cracking.
- The foundations: what can be seen of the depth and the ground, and any sign of settlement.
- The house wall: the line where the roof will meet it, and what that wall can hold.
- The existing roof: the structure, its weight, and how it was fixed.
- The floor and any drains near the base of the walls, where wet ground can affect the footings.
Cracks matter, but their direction and width matter more than their presence. A hairline crack in a dwarf wall mortar joint is one thing. A stepped crack that has opened over time suggests movement, and a heavier roof would add to it. We record these, and if the signs point to movement we advise asking a structural engineer to look before any decision is made.
Our page on whether dwarf walls will take a tiled roof deals with that part in more detail.
We cannot see inside a dwarf wall or below the ground. When the survey leaves a doubt, we recommend an engineer rather than guess, and we hold the roof order until the answer is in.
Building Regulations and energy rules, England and Wales
The Planning Portal says: "A new roof must comply with building regulations to ensure it is structurally safe, energy efficient and properly ventilated." So put the plan to your building control body before you order a solid roof. Building control is the council's service or a registered building control approver.
Some conservatories are exempt from the energy rules. In England, paragraph 0.14 of AD L sets out the conditions, and all of them must hold:
- the floor sits at ground level
- its floor area "does not exceed 30m2"
- the glazing meets Part K
- any wall, door or window that separates it from the house is still in place, or has a replacement
- the house's heating has not been carried into the conservatory or porch
If the conservatory is not exempt, the roof is a thermal element, and the figures for a replacement roof on an existing house apply. In England, AD L 2021 Table 4.2 gives 0.15 for a roof. In Wales, the Welsh AD L Table 4.1 gives 0.13. Roof windows are 1.4 or WER Band B, and rooflights 2.2, on both sides of the border.
AD L 2026 takes effect in England from 24 March 2027, and the new Welsh AD L from 4 March 2027. Until those dates, the editions above apply. In Wales, the Welsh Approved Document L sets its own exemption (paragraph 0.16), including a floor area under 30 m2 and no fixed heating appliance, so ask the council how it applies.
Our page on when a conservatory is exempt covers the exemption in full.
Planning, listing and conservation areas
Planning is separate from the Building Regulations. A change from a light roof to a solid one alters how the building looks, so the planning position is worth checking before work starts. We state the rule for each side of the border without over-claiming.
In England, permitted development Class C covers an alteration to the roof of a dwellinghouse, and England's Class C carries no condition on matching materials. In Wales, Class C in the 1995 Order asks for materials that match the existing in appearance so far as practicable, and a change from polycarbonate to tile alters the appearance. In Wales, check with the council or with the National Park Authority whether a solid roof needs an application.
Class C does not remove the need for consent in protected places:
- In England, a listed house keeps its permitted development rights but also needs listed building consent under section 7 of the Planning (Listed Buildings and Conservation Areas) Act 1990.
- In Wales, the Historic Environment (Wales) Act 2023, sections 88 and 89, applies to a listed building.
- In a conservation area, ask the council whether an Article 4 direction applies to your address.
A flat or maisonette has no householder permitted development rights, because the Order leaves buildings containing flats out of the word dwellinghouse. A conservatory attached to a flat therefore needs the council's view from the start.
For roof windows in the new roof, our planning guide on roof windows in England and Wales gives the conditions on each side of the border.
If the frame cannot take it: the lighter routes
A no from the survey does not close the project. Three routes keep the load down or deal with it.
The first is a lightweight tiled system, made to a lower weight per square metre than a built-up roof. Our page on lightweight tile systems explains how those are specified. The second is a new glass roof, which is light and suits a frame that was made for glazing. The third is strengthening the frame and the walls to an engineer's design, which is only worth it when the cost and the disruption suit the project.
The lifespans of the choices differ, and HomeBuilding gives them as typical figures, not promises, with the glass and tiled lines quoted from Roofing Megastore's managing director:
- polycarbonate: "a typical lifespan of 10 years"
- glass: "will likely last in excess of 30 years"
- tiled: "will typically last in excess of 50 years"
On cost, MyJobQuote gives the average conservatory roof replacement as between £3,200 and £6,000 in 2026. That range covers all types, and your frame may add to it or take away from it. You get the written total once the survey is done, with the scaffold inside it.
Sometimes the answer is a repair. A cracked panel or a worn seal does not need a new roof.
Whichever route suits, the order is the same: survey, photographs, a structural opinion where one is needed, approval from building control, then a written total price. Nothing is ordered before the approval question has an answer, because a roof made to measure cannot be returned.
What an engineer or building control will want to see
If the survey points to a solid roof, the next step is paperwork, and a good set of facts makes it quicker. An engineer or a building control officer may ask for the same few things.
- Dimensions of the conservatory and the height of the dwarf walls, with photographs of the walls from both sides.
- The make-up of the proposed roof, layer by layer, with its weight per square metre from the supplier's data.
- The weight and construction of the roof being removed.
- Photographs of the frame joints, the base of the posts and the junction with the house wall.
- Any signs of movement: cracks, gaps at the door frames, or sticking doors.
We prepare the photographs and measurements from the survey and pass them to whoever needs them. If the engineer asks for trial holes to see the foundations, that is a separate job and the owner commissions it.
- Photographs are labelled with the wall or post they show.
- Measurements are given in millimetres, from a fixed point.
It also helps to say what the room is for. A conservatory used as a living room, heated from the house, is a different case from a cold garden room, and the answer changes the energy rules above.
If the answer from the engineer is that the frame can take a solid roof only with strengthening, we set out the options and the written total for each, so the two routes can be weighed against each other before you decide.