Replacing a conservatory roof looks like a quick swap when you watch from the garden: the old covering comes off and the new one goes on. In practice the job is a chain of stages, each one resting on the last, and it helps to know the chain before anyone arrives with a ladder.
This walkthrough follows the order of a replacement, from the paperwork that comes first to the handover at the finish. It promises no count of days, because the length of a job turns on the roof's shape, the covering chosen and the state of the frame. What it does show is what happens at each stage, what you will see on site and where the rules of each country come in. Each rule is tagged England or Wales in the sentence that gives it.
The service itself is described on our conservatory roofs page. For the approval questions, our post on the conservatory roof replacement rules takes them one at a time.
Before the first day: rules, survey and paperwork
The job begins well before any panel is lifted. The survey comes first. On it we study the frame, the base, the joint with the house wall and the gutters, and pictures are taken of each fault on the building itself, to go with the written price. The written price that follows is a single total.
Then come the rules, which differ by country:
- In England, the Planning Portal's guidance is that any replacement roof on a conservatory has to meet building regulations, so building control is asked before a covering is ordered.
- In Wales, the Welsh Government says of re-roofing that "In most situations, this work will need Building Regulations approval."
- In England, a replacement covering that adds weight "by 15 per cent or more" needs approval under the Planning Portal's test, while Approved Document A speaks of "more than 15%". In Wales, the Welsh Approved Document A also says "more than 15%".
One way weight rises is a solid roof going on in place of glass. That is a matter for Building Regulations, not planning, and it is why the frame is assessed before anything heavier is ordered.
An exempt conservatory still has structure and ventilation to satisfy. Where it is not exempt, the energy figures apply as well: in England Table 4.2 of Approved Document L gives a new roof 0.15, and in Wales Table 4.1 gives 0.13. Building control tells you which case you are in.
Last comes the contract. A start date and a written total go on one page. Ask for both, and read what the price includes before you agree to anything.
First day on site: stripping the old roof
The opening stage is removal. Nothing new goes on until the old roof is off and the frame beneath it has been looked at properly, because a frame that cannot carry the new covering changes the plan.
For a glazed or polycarbonate roof the sequence runs as follows:
- Clear the room of furniture and cover the floor, and wrap anything that cannot be moved.
- Lift off the old sheets or glass units starting at the ridge, and lower each to the ground instead of dropping it.
- Remove the ridge and cresting, where the roof has them, and the old gutter beading.
- Strip the worn sealant strips and capping from the glazing bars.
Glass is heavy and breaks into sharp pieces, so it is lifted with suckers and carried out whole where possible. Polycarbonate is light, but it flexes and cracks if someone stands on it.
With the covering gone, the bars are inspected. Rot in a timber frame, corrosion in an aluminium one or movement in the dwarf walls shows now, and each is photographed. A sound frame goes forward. One that is not sound is raised with you before anything is fixed to it.
The work also needs access, meaning a clear route from the gate or side passage to the garden for ladders, panels and waste. Tell us at the survey about steps, narrow gates and parked cars, so the route is planned instead of discovered on the day.
The roof is never left open. Before the crew leaves each evening the frame is sheeted over, so the room stays dry until the next visit.
The middle stage: the new roof goes on
With the frame passed, the new roof is built up from the eaves towards the ridge. What is fitted depends on the covering, and so does the expected lifespan. HomeBuilding gives a typical figure for each of the three, quoting Roofing Megastore's managing director for glass and tiled:
| Covering | What is fitted | HomeBuilding lifespan |
|---|---|---|
| Polycarbonate | Sheets in bars, with sealed ends | "a typical lifespan of 10 years" |
| Glass | Glazed units on bars, bedded and capped | "likely last in excess of 30 years" |
| Tiled | Battens, underlay and tiles on a stronger frame | "typically last in excess of 50 years" |
These lifespans describe a typical roof from a single source. None is a promise for yours.
On a glazed roof the bars are fixed first, then the units follow from the eaves upwards so that each overlaps the one below. The caps are screwed down over a seal.
A tiled roof follows the order used on a house. Battens go on, then underlay, then tiles course by course. The ridge is fixed mechanically. Marley notes that since the 2015 amendments to BS 5534, mortar "could no longer be relied upon as the only means of securing the roof covering", so a ridge that depends on mortar alone falls short. On a solid roof the frame may need strengthening before the load goes on. That work is done and checked ahead of the battens, never after them. Ask for the order of work in the quote, and expect it to shift if the weather turns.
The final stage: lead, gutters and the clear-up
The last part of the job is the part that keeps the weather out for years. The wet joints are done once the roof is on, because they depend on it.
- The flashing along the house wall is cut into a chase, wedged and pointed, with soakers where the covering is tile.
- The roof edges and corners are sealed and capped.
- The gutters are refitted or renewed with a fall that drains them; Brett Martin gives "1mm for every 600mm".
- The downpipes are checked, and the outlets cleared.
We deal with lead and drainage in more depth in the pages on leaks at the house wall and gutters and lead on conservatories.
Then the site is cleared. The old covering and offcuts go away with us, the path and patio are swept, and the room is left as we found it, minus the old roof. Before leaving we photograph the finished roof and each joint, so you hold a record of what was fitted.
That record is worth keeping. If building control was asked about the work, it shows what was done, and it helps if the house is sold and a buyer wants to know what was fitted and when. A tidy site and a set of pictures are the last things we hand over, after you have walked round with us and looked at each joint.
Anything you spot on that walk-round is dealt with there and then, while the crew is still on site, so there is nothing left to chase afterwards.
What moves the timetable
Nobody can honestly promise a number of days before the frame is open. Several things move the timetable, and the written quote should say how each is handled:
- the size and shape of the roof, since a roof with several facets has more bars, joints and flashings than a lean-to
- the covering, because a tiled roof has more courses and more fixing than a sheet or a glazed unit
- the state of the frame once the old covering is off
- wet or windy weather, because an open roof is not worked on in either
- the wait for made-to-measure glass units to arrive
When scaffold must go up on the public highway, a licence must be in place before it goes up, under section 169 of the Highways Act 1980. We arrange the licence with our scaffolder, and the fee and the notice period belong to the council that grants it. Check with the council for the current figures. Where a scaffold is needed, it is part of the written quote.
A job that pauses for weather has not fallen behind. It is waiting until the roof is safe to work on, and that wait protects the room below as much as it protects the people on the roof. Ask what the plan is for each stage in poor conditions, because a clear answer tells you how the work is run. A programme drawn up with weather in mind is worth more than one that assumes dry days.
What it costs, and how to read a quote
Typical UK ranges from third parties, and never our prices, give a sense of scale. MyJobQuote reports that in 2026 the average conservatory roof replacement costs between £3,200 and £6,000. The covering, the size and shape of the roof, the state of the frame and access all move a real job within that range or beyond it.
When you hold two quotes side by side, compare what each covers rather than the total alone:
- the covering named, with the type of glass or the thickness of the sheet
- whether the frame, the bars and the capping are being replaced or reused
- whether the lead at the wall and the gutters are included
- whether scaffold, waste removal and VAT are in the figure
- the order of work, and what happens if the frame needs repair
A quote that gives one total with a plain account of the work behind it is easier to hold a firm to than a string of separate stage prices.
Payment terms belong in the written quote too: when each payment falls due, and what it is for. A firm that is clear about that before work starts is easier to deal with when the roof is half on.
If a firm will not put its price in writing before starting, ask why before anything is signed. A written total is a courtesy to you, and it is also the cleanest way to settle what was agreed if a question comes up later.