A roof replacement stands or falls on its scaffold. Without a proper platform at the eaves, nobody can strip a slope safely, carry slates up without a ladder, or fix a gutter at the end. With one, the work runs in a clean sequence from the ridge down.
It is also the first thing the neighbours and the council notice. If it stands on the road or the footway it needs a licence, and the licence carries its own fee, its own notice period and its own rules, which differ from one council to the next. Some of those councils are in England and one in our patch is in Wales, so the figures below are labelled with the council that publishes them.
We arrange the licence with our scaffolder. What you need to know is how it shapes the dates, what it can add to the bill, and what to ask your quote to say. The wider job is described under roof replacement.
What the scaffold does on a re-roof
On a replacement the scaffold has four jobs, and each one affects how it is built.
- It gives a level, boarded platform at the eaves, so the crew works behind a guard rail and not from a ladder.
- It carries edge protection round the whole roof, including the gable ends and any extension.
- It gives a route for materials, so slates, tiles and battens go up on a hoist or by hand without being thrown.
- It holds the clearing-up: loose debris from the strip stays on the boards until it goes down in a chute or sack.
The shape of the roof decides the shape of the scaffold. A hipped roof needs the platform to turn the corners. A house with a rear extension needs a lift of boards at a different height. A tall chimney may need a separate tower, and a gable end may need a full lift up the end wall so the verge can be reached from the side.
Ties hold the frame to the wall, and we agree where they can go before the scaffolder arrives, so any fixing point that has to be made good afterwards is known in advance.
It stays up for the whole job, not only the strip-out. The same platform is used to lay the covering, dress the lead, fix the ridge and hang the gutters at the end. Edge protection also stops tools and loose slates sliding off the eaves onto whoever is below. Because it is in place from the first day to the last, the dates for putting it up and taking it down set the dates for everything else, and any licence needed has to cover that whole span.
When the street gets involved
Scaffolding is on private land until it reaches the highway. The moment a pole stands on the footway, the verge or the carriageway, or a board or sheet overhangs it, the law changes. Section 169 of the Highways Act 1980 says that no person shall "erect or retain on or over a highway any scaffolding or other structure which obstructs the highway" without a licence. The Highways Act 1980 covers both countries.
It is a scaffold licence, granted by the highway authority for the area.
Three cases show how the rule plays out:
- A terrace or a house at the back of the footway: the scaffold sits on the public pavement, so a licence is needed.
- A house set back behind a garden or drive: the scaffold stands on your land, and section 169 does not bite unless it overhangs the highway.
- A corner house or a house on a narrow lane: part of the frame may reach the highway even though most of it is yours.
If you are unsure which applies, the council's highways team can say. We measure at the survey and report what we find, so the licence question is settled before a date is set. Herefordshire Council's page treats a cherry picker or hoarding on the highway in the same way as scaffold.
Our guide to re-roofing a terraced house shows how this works on a street where nobody has a front garden.
What each council charges, and how much notice it wants
Fees and timetables vary from council to council, because some charge per week, some per month and one a single sum. The table gives each council's own figure with its own unit. Do not compare one row with another as if the units matched.
| Authority | Charge | Lead time |
|---|---|---|
| Herefordshire (England) | £167 (a maximum of 1 month); £123 per month to extend | At least 10 days |
| Worcestershire County Council (England) | £85 per week, £65 for subsequent weeks, £25 urgency surcharge | Not set out in days |
| Gloucestershire County Council (England) | £145 for a minimum period of 28 days, £36 per 7 days to extend (prices from 1 April 2025) | At least twelve calendar days |
| Shropshire Council (England) | £200 for a scaffolding or hoarding licence | Ten working days at least, Saturdays excluded |
| Monmouthshire County Council (Wales) | £108 administration fee; £27 per week to extend | At least 5 working days |
Powys is not in the table: ask Powys County Council for its scaffold licence terms. Each fee is for the licence only, not for the scaffold itself, and fees change, so we confirm the current figure when the date is fixed.
Worcestershire County Council's page is the only one that names who applies: in its words, the firm hired to do the work puts the licence in its quote because "they are required to apply for licences". For the other councils we arrange the licence with our scaffolder and tell you the council's fee up front.
Where the licence sits in the timetable
A licence is a date constraint more than a cost. Nothing goes on the highway until the council has granted it, and the notice periods in the table are minimums, counted from the day an application is complete.
The councils word their process differently. On its road occupation licence page, Herefordshire Council says: "We aim to process your application within 10 days of receipt." and "Tacit consent does not apply." That means a start date cannot be assumed from silence. Shropshire Council asks for ten working days, excluding Saturdays, and lists market-town embargo periods, including Christmas and Good Friday. Monmouthshire County Council asks for five working days and sets an administration fee of £108.
Putting the dates together, the sequence is:
- We survey and measure where the frame will stand.
- You agree the written price and the approximate start.
- The licence application goes in with enough notice for the council in question.
- The scaffold is erected once the licence is granted, and the strip-out begins.
- If the job runs past the licence period, an extension is applied for before the old one ends.
Retrospective applications cost more. Herefordshire Council lists £335.50 for one month on that route. Worcestershire County Council lists a £25 urgency surcharge for applications made within 2 days. We build the timetable so neither is needed.
Weather can push a start back a few days, and an extension then covers the overrun. We allow for that when we set the licence period.
Access, neighbours and the footway
The licence lets the scaffold stand on the highway. It does not tell the neighbours, and it does not decide where the lorry parks or how the crew reaches the back garden. Those are practical points to settle at the survey.
The questions we ask on the doorstep are:
- Can the frame stand wholly on your land, or does it need to reach the footway?
- Is there a side passage, a gate or a garage through which materials can reach the back?
- Do vehicles, bins, planters or low walls need moving before the scaffolder arrives?
- Where do people walk past, and does the frame need a boarded walkway or netting at that point?
- Are there windows, gutters or satellite dishes that should be protected or taken down first?
On a terrace the pavement is all there is, and a walkway can be built through the frame so pedestrians still pass. Where the footway is narrow, we raise it with you at the survey, before the licence is applied for.
Tell your neighbours before the scaffold goes up. A short note with the dates, the contact number and a line about access saves a good deal of friction. We keep to the days we give, and tell you if a date moves.
The scaffold also needs somewhere to stand on soft ground. Boards under the standards spread the load, and we mark any drain covers or pipes we find so they are not built over.
What your quote should say about scaffold
A quote should say plainly that the scaffold is inside the price. When you compare quotes, these are the points to check:
- whether the scaffold and its erection and removal are included in the written price
- whether the licence fee is included, where a licence is needed
- whether VAT is included, or added at the end
- what happens if the job runs past the licence period, and who bears the extension fee
- whether the quote names the council whose licence terms apply
- who clears the footway and sweeps the kerb once the frame is struck
- that the frame stays until the gutters and fascias are finished
Ask, too, when the frame will come down. It should stay until the roofline work is finished, and not leave early to suit someone's calendar. A quote that leaves these points out leaves a gap that tends to be filled later. We state them in the written price so that nothing about the scaffold arrives as a surprise halfway through the job.
The written price covers the scaffold, and any licence fee is the council's own.
For the main job, the order of work from strip-out to sign-off has its own page, a roof replacement stage by stage, and the old covering's journey off site is covered in what happens to the old roof.
Finally, take the dates in writing. A start date that depends on a licence is a date with a condition, and the condition should be written next to it.