01432 610152 Get a quote Call 01432 610152

Construction phase plan

Does a Re-Roof need a construction phase plan?

Yes. Even a house re-roof needs a construction phase plan, and the duty to produce it moves from the homeowner to the firm doing the work.

In brief

Yes. CDM 2015 regulation 15(5) says that when one contractor is working on a project, that contractor has to prepare the plan, or have it prepared, in good time before the site is set up. A homeowner is a domestic client, and regulation 7(1) hands the client's duties on to the contractor. England and Wales are treated alike. How big the job is changes how long the plan runs, not whether one exists.

Who counts as the client, and who carries the duty

HSE's domestic-client page describes a person having building work done on their own home, or a relative's, outside any business. A homeowner paying for a re-roof fits that exactly. A landlord letting out the same house is in a different position, because letting is a business.

The Regulations do not expect a householder to run site safety. Regulation 7(1) moves the client's main duties to another party, and which one turns on the shape of the project:

  • a lone contractor takes them if there is only one on the project
  • with several, they sit with the principal contractor
  • a principal designer holds them if the homeowner has agreed that in writing

On an ordinary single-firm re-roof, then, the duties land on the firm whose crew is on your roof. You are not asked to write anything, though you are entitled to ask what has been written and to read it before the scaffold arrives, and to say so if something in it does not match your house. A plan that exists only in someone's head is not a plan, and a firm that cannot show one has not yet done the preparation.

What goes into the plan for a re-roof

The plan is the written account of how this particular site will be run safely. For a re-roof, ours deals with the matters a roof raises:

  • scaffold: who puts it up, whether a highway licence is involved, and how the edges are guarded
  • the roof itself: how people get on and off, and how weak areas are crossed or avoided
  • stores and waste: where materials sit and how rubbish leaves the site
  • the people close by: your household, the neighbours and anyone walking past
  • unknown materials such as asbestos, and what halts the work if one turns up

HSE calls every asbestos cement roof fragile and wants a lockable skip for asbestos, so both belong in the plan for an older garage or outbuilding. If the scaffold needs a licence, we arrange the licence with our scaffolder, and the plan notes that this was settled before erection.

We write the plan to fit your roof, after the survey and before the first delivery, so the scaffold position and the skip position are decided on paper first. If the plan changes during the job, because the roof timbers turn out worse than expected or a neighbour needs access, the changed page replaces the old one and you are shown it.

One contractor or several

What separates a simple project from a bigger one is the number of contractors, not whether the job is notified to anyone. The extra duties turn on there being more than one firm. A plan is required either way, because it is required of every project.

That matters on a re-roof where other trades arrive: an electrician for solar panels, a plasterer once a roof window is in, or a separate scaffold firm. With a second firm on site, the client's duties move to the principal contractor, who co-ordinates the plan across the trades. As the homeowner, you should be told who that is.

Three questions cost nothing to ask. Who is the contractor? Who else will be on site? Who holds the plan? A clear answer to all three is the sign of a firm that has done its thinking before arriving. The answer is the same in Hereford and in Monmouth, because these Regulations cover the whole of Great Britain, not one country.

On a single-firm job, the roofer is the contractor, and the question about a principal contractor falls away. Even so, ask early. A job can start as one firm and grow a second when a hidden fault, a chimney rebuild or a new roof window brings another trade onto the site mid-way.

What you can ask to see before work starts

A homeowner carries no duty here, but a plan is a document you can request. Four requests are reasonable:

  1. A copy of the plan prepared for your roof.
  2. The name of the party holding the client's duties.
  3. The route that materials and waste take in and out.
  4. How the work stops, and who is told, if a surprise appears such as asbestos or a bat roost.

Two other matters sit apart from it, and both can be confused with it. Building Regulations approval follows each side of the border's own test, and the VAT domestic reverse charge is limited to the Construction Industry Scheme, where it moves between businesses, and a homeowner never pays it. Neither alters your duties here.

The price comes first, as one written figure once the survey is done, and the plan follows it from there. Ask the contractor to confirm that the plan covers the scaffold and the skip, since both need someone named to look after them. Related reading: scaffolding for a roof replacement and the stage-by-stage account. The whole job is under roof replacement.

Related questions

Do I write the plan myself as the homeowner?

No. As a domestic client you pass the duties on under regulation 7(1), and the party who receives them depends on how many firms are working. You are not expected to produce the plan, but you can ask to read it before work starts and keep a copy afterwards, along with the rest of the job's papers.

Does a small repair need a plan too?

The requirement covers every project, and nothing in the Regulations excuses a small one. A repair visit is shorter, so its plan is shorter, perhaps a page on access and the roof edge. A full re-roof needs more, because it brings scaffold, waste removal and a longer stay on site.

Get your free roof quote

Tell us about the roof and we will arrange a survey.

10-year workmanship guarantee, in writing