In brief
In England, Approved Document L paragraph 0.14 asks that whatever separates the two is kept or, if it was taken out, put back. A door removed with nothing fitted in its place fails that condition, so the room stops being exempt and a new roof must meet the full roof figures. Fitting a door, wall or window back into the gap is what the wording asks for. In Wales, ask the council's building control service or a registered building control approver to confirm the Welsh position.
What the wording asks for
The condition is short. In England, the divide between house and conservatory must be "retained", or if removed, "replaced". It has two ways to pass and one way to fail:
- Retained: the original wall, door or window is still in the gap.
- Replaced: it was taken out, and something now sits there instead.
- Failed: it was taken out and the gap was left open.
The reason is practical. A conservatory that can be shut off from the house is treated as a separate, lightly built room, outside the energy rules. Once the two share one open space, the room behaves as part of the house and is treated that way, with a heating system that serves both. That is a reading of the wording, so check it against your own case with building control before you rely on it.
The test looks at the gap itself. Whether the old door was good or poor does not matter, and nor does how long ago it was removed. What matters is whether something closes the opening today.
Open-plan, knock-through and half measures
| What was done | Against the condition |
|---|---|
| Original door left in place | Retained |
| Old door swapped for a new door | Replaced |
| Door removed, opening left clear | Not met |
| Whole wall taken out for open-plan living | Not met, unless a wall, door or window goes back |
| Door removed, glazed screen added later | Looks like replaced; confirm with building control |
A house bought with a knocked-through conservatory may have been opened up long before you arrived, and the paperwork may not say. If you are unsure, photograph the opening, measure the room, and ask building control how the room is treated now.
Taking out the wall between house and conservatory is structural work, so building control is asked before the wall comes out and not afterwards. The same goes for a new opening where there was a window.
Sliding or folding doors set in the old opening count as doors in the gap, but confirm that with building control too, since the wording says nothing about the type of door.
What changes once the exemption is lost
With no exemption, the energy rules reach the conservatory, and a new roof has to meet the figures set for new roofs on existing houses. In England, Table 4.2 of Approved Document L 2021 gives 0.15 for a roof, with roof windows at 1.4 or WER Band B and rooflights at 2.2. In Wales, Table 4.1 of the Welsh Approved Document L gives 0.13 for a roof, with the same window figures.
In practice that means choosing a roof build-up that reaches those numbers, not a single skin of polycarbonate or glass, and checking the frame can carry it. The lead at the house wall is renewed in the same visit, because it is much easier to do with the old roof stripped. The Planning Portal's line for England covers any roof change on a conservatory: the roof has to comply.
A room with no door between it and the house also tends to be heated as part of the house, which raises the heating question covered on our heating page. Our page on insulating a conservatory roof sets out the routes to the roof figures.
Putting the separation back, and where Wales fits
If the gap is open and you want the exemption, the England wording points to one remedy: fit a wall, door or window back into the gap. Whether that restores the exemption for a particular room is for building control to confirm, so describe the work, send photographs, and keep their reply in writing. They may also want to see the glazing, because the other conditions are tested at the same time.
If you would rather keep the open-plan room, plan the roof as a roof for a living space from the start. We photograph the junction at the house wall at survey, so the lead, the structure and the state of the wall plate can be seen before a roof is priced.
For Welsh addresses, including the Bannau Brycheiniog National Park, paragraph 10.34 of the Welsh Approved Document L says the exemption ends when the separating walls, windows or doors are removed and not replaced. Ask the council's building control service or a registered building control approver how a taken-out wall or door is treated there, and whether the conservatory has to meet the roof figure of 0.13. The conservatory roofs hub lists the other questions to settle, and the 30 m2 limit is the sister page to this one.