Principal contractor

When does a job need a principal contractor?

Under the CDM Regulations 2015, a second contractor on site means a principal contractor must coordinate. A lone contractor takes on the duties alone.

In brief

The test is a head count of contractors. A project with a single contractor puts the duties on that firm, which must arrange a construction phase plan. Once a second contractor joins, a principal contractor is needed, the one who coordinates the construction phase. The Construction (Design and Management) Regulations 2015 apply across Great Britain, so the rule reads alike for a Hereford yard and a Welsh border one. Notifying the project to HSE is a separate matter.

One contractor or several: the test

CDM 2015 asks a simple question first. Is there one contractor on the project, or more than one? Everything else follows from the answer. A contractor is any business doing the building work, so a roofer, a scaffolder, an electrician fitting roof-mounted plant and a specialist lifting asbestos sheets are each a contractor if each is engaged to work on the project.

Where a single firm does all the work, the rules put the planning on that firm. Regulation 15(5) says the contractor "must draw up a construction phase plan, or make arrangements for a construction phase plan to be drawn up, as soon as is practicable prior to setting up a construction site". The plan is short on a small job and longer on a large one, but it exists on every project.

Where a second firm arrives, a principal contractor has to be in place to coordinate between them. The extra duties turn on the number of contractors, not on whether the project is notified. That point is easy to get backwards.

Who the client is makes a difference

CDM 2015 gives duties to the client, and the kind of client matters. HSE says: "A domestic client is any individual who has construction work carried out on their home, or the home of a family member, that is not done as part of any business." A shop, a unit, a farm building or a flat roof let to a tenant does not meet that description, because the work serves a business.

The distinction decides who carries the client's duties:

  • A domestic client's duties pass under regulation 7(1): to the lone contractor, to the principal contractor on a multi-firm project, or to the principal designer if there is a written agreement.
  • A commercial client keeps the client duties, and appoints the principal contractor once a second firm is on the roof.

If you own or manage a commercial building, expect to be asked who is coordinating the work, and ask the same question of us. Our commercial roofing page explains how a job is scoped, and the survey records what trades the roof will need.

How a roof job turns into several contractors

A roof replacement can start with one firm and become a project with several. The roofer is the obvious contractor, but others arrive alongside:

  • a scaffold firm erecting access, with the licence for any scaffold over the pavement arranged through our scaffolder
  • a specialist firm taking off asbestos cement or asbestos insulating board
  • an electrician disconnecting and refixing roof-mounted equipment
  • a company supplying and fitting new rooflights or smoke vents
  • a separate gutter or cladding contractor on the same elevation

Whether those count as separate contractors depends on who engages them. If the client appoints each one directly, the project has several contractors and needs a principal contractor. If one firm engages the rest as its own sub-contractors, the arrangement on the project may differ. Ask the person managing the project to say in writing who holds each role, because a vague answer on the day is hard to untangle afterwards. Our answer on who can go up on an industrial roof shows why that matters, since coordinating access is the heart of the role.

England and Wales: what stays the same and what moves

CDM 2015 is a Great Britain regulation, so a warehouse near Hereford and a workshop near Abergavenny face the same test, the same regulation 7 and the same regulation 15(5). The border does not change who needs a principal contractor. It changes some of the things the principal contractor has to coordinate, such as approvals, waste and the order of trades on the roof:

  • In England, the Planning Portal sets its re-roofing test as less than 25 per cent of the building envelope and less than 50 per cent of the roof, in guidance written for houses.
  • In Wales, the Welsh Government says re-roofing in most situations needs Building Regulations approval.
  • On waste, England and Wales keep separate carrier registers, and NRW runs the Welsh one.

Under section 169 of the Highways Act 1980, a scaffold over the highway needs a licence, and we arrange the licence with our scaffolder. The cost of the scaffold is carried in the single written price that follows the survey, and the coordinating role is named well before the poles go up. Those licence rules come from the road authority, which is a different council on each side of the border.

Related questions

Does the VAT reverse charge change who is the principal contractor?

No. The domestic reverse charge is a VAT rule that applies only to building services reported under the Construction Industry Scheme, and CDM is a health and safety regulation. The two sit side by side. A homeowner is never charged under the reverse charge, and a business client should ask its own adviser how it applies to the invoice.

Can the client act as principal contractor?

The regulations give the role to a contractor, so a commercial client normally appoints one of the firms on site to hold it. What matters is that one party is named in writing as coordinating the construction phase, with a plan in place before work begins. Ask for that name when the quote is accepted.