01432 610152 Get a quote Call 01432 610152

Shop and flat roofs

Roofs on shops with flats above: access, drainage and neighbours

A shop with flats above puts a roof, a pavement and several households into one job. This guide covers how we reach the roof, where the rainwater goes and who must be told first.

Horizon Roofing Hereford 9 min read

A roof over a shop with flats above may not be one plain pitch. It tends to be a mix of parts: a main roof, a parapet along the street front, a lower rear roof over the stockroom, and chimney stacks or a party wall shared with the building next door. Each part can have a different owner, a different drainage route and a different neighbour to think about.

We survey it from the top down, the same way as any roof, starting at the parapet, the stacks and the valleys. Because the building stands on a street, we look at the ground as well: where a scaffold can stand, where the pavement runs and what the shop needs in order to keep trading.

The sections below take access, drainage, approvals, neighbours and site safety in turn, and every rule carries its country in the sentence that gives it. Roofs like this sit inside our commercial roofing work, and the questions here are the ones to settle before a written price is agreed.

Reaching the roof from a busy street

Access decides more on this kind of building than the roof itself. A shop front leaves no garden to set a ladder in, so a scaffold goes on the pavement or the carriageway. Section 169 of the Highways Act 1980 covers scaffolding erected above a public road or pavement; the licence is something we arrange with our scaffolder. Fees and notice periods vary by council, and their units differ, so the figures below are never compared with each other.

  • Herefordshire Council: £167 per licence, over a maximum of 1 month; extra months cost £123 per month; at least 10 days' notice.
  • Monmouthshire County Council, in Wales: an administration fee of £108 and £27 per week to extend, with at least 5 working days' notice.
  • For a Powys street, the council's own highways team gives the fee and the notice.

The written quote already carries the scaffold, so a licence fee does not arrive as an extra. The licence period is worth a thought before the quote is signed, because a spell of bad weather that runs past it means an extension.

Inside the building, the way up can be the flats' common stair, a roof hatch or a window onto the rear roof. Each of those passes through someone's home or a shared hallway, so we agree the route in advance and protect the floor. Where the only way up crosses a shop stockroom, we plan the work around the shop's opening times, not around ours.

Deliveries of tile, lead and membrane need a place to stop. A hoist on the street front takes some of the pavement, and the licence has to cover it.

Parapets, box gutters and where the rain goes

On many shop buildings the rainwater does not fall into a gutter on the eaves. It runs into a parapet gutter, a channel behind the low wall along the street front, or into a box gutter between two roofs. These are internal gutters. They empty through an outlet into a downpipe that may run inside the wall or down the back of the building, and a blocked outlet backs the water up behind the parapet and into the building.

That is why a stain on a flat's ceiling can come from the street front rather than the middle of the roof. Our guide to valley and box gutters on commercial roofs covers the linings in detail. On this building type we check these things first:

Where the stain shows and what we check
Stain in the flatFirst check on the roof
Front room, near the wallParapet gutter and its outlet
Between two roofsBox gutter lining and joints
Rear bedroomLower roof abutment and downpipe
Shop ceiling belowFlat roof over the stockroom

Falls matter in an internal gutter. NFRC says BS 6229:2025 sets "a minimum 1:80 finished fall for general roof areas and internal gutters", and the standard covers membranes only, so a lead-lined gutter sits outside it. For the visible gutters at the rear, Brett Martin gives "1mm for every 600mm".

Rear downpipes need a look as well. A pipe that is cracked, or that discharges against the wall of the next building, causes damp that looks like a roof fault.

Approvals: what England and Wales each ask

The rules change at the border, and a shop with flats above is not treated as a house under either set. These are the points to ask about:

  • In England, the Planning Portal asks for Building Regulations approval when a new covering is heavier "by 15 per cent or more", and AD A puts the same threshold as "more than 15%".
  • In Wales, the Welsh Government says of re-roofing: "In most situations, this work will need Building Regulations approval."
  • In England, the Building Regulations 2010 list the roof among the thermal elements, and AD L 2021 puts a new flat roof membrane under renovation.
  • In Wales, AD L Table 11.1 asks for a renovated roof at 0.16, and not worse than 0.35 where 0.16 is not feasible.

Planning is separate. In England, the General Permitted Development Order 2015 excludes a building containing flats from the word dwellinghouse, so a flat has no householder permitted development rights. In Wales, ask the council before assuming a roof alteration needs no application.

If the building is listed, consent is needed as well. In England, that is listed building consent under section 7 of the Planning (Listed Buildings and Conservation Areas) Act 1990. In Wales, the Historic Environment (Wales) Act 2023 applies through sections 88 and 89. Many shop buildings stand in conservation areas, so check with the council.

Building control is either the council's service or a registered building control approver. In Herefordshire, that means Herefordshire Council Building Control on 01432 261938. In Powys, write to the council's building control service or a registered building control approver.

Neighbours, shared stacks and the building next door

Terraced shop buildings share walls and can share stacks. Work to a shared wall falls under the Party Wall etc. Act 1996, which covers both England and Wales. Serving the notice is the owner's duty, and no roofer can do it for them. Notice goes out at least two months ahead for work to a party wall, for instance trimming back a chimney breast (section 2(2)(g) and section 3(2)(a)), and at least one month ahead for a new wall on the line or nearby excavation (sections 1 and 6).

Written consent from the neighbour is possible under section 3(3)(a). After a notice, an objection from the neighbour or 14 days of silence brings in a surveyor (sections 5 and 10). Party wall questions go to a party wall surveyor, not to building control.

Who counts as the building owner in a block of flats depends on the leases and on who holds the freehold. We cannot settle that from the roof, so the leases are worth reading with a solicitor before the survey. It saves a stalled job later.

Neighbours also feel the work in other ways:

  • noise on the scaffold and from the hoist, which sits on the same street
  • a licensed scaffold that narrows the pavement outside the next shop
  • dust and debris falling onto the adjoining roof
  • access across a shared yard to the rear roof

We tell the next building's occupiers what is coming and when. A skip, a hoist or a stack of tile is easier to place when the neighbour has already said where they need clear space.

Site safety, asbestos and nesting birds

A roof over occupied flats cannot be left open overnight. We strip and cover in sections small enough to be made watertight by the end of each working day, and the flats' occupiers are told which sections are coming. Photographs of what we find under the old covering come to you before anything is agreed.

Three duties come with the job.

  1. CDM 2015 regulation 15(5) gives a sole contractor the construction phase plan. HSE describes a domestic client as an individual having work done on their home, outside any business, so a shop owner or landlord sits outside that wording while a flat owner living in the flat sits inside it. For a domestic client, regulation 7(1) passes the client's duties to the contractor.
  2. HSE says: "If the building was built or refurbished before 2000, assume that there is asbestos in it." It also says "AC roofs are always fragile", and our guide to fragile roofs and rooflights covers that risk. Any asbestos goes into a lockable skip, as HSE advises, and never an open one.
  3. An active wild bird's nest, including one still going up, is protected by section 1 of the Wildlife and Countryside Act 1981 against a person who "intentionally" destroys it, takes it or damages it. Bats are covered by a separate licence system, from Natural England in England and Natural Resources Wales in Wales.

Parapets and the edge of a roof over a street need edge protection, because anything dropped lands on the public. The scaffold design covers it, and the licence terms apply.

The survey, the written price and living with the work

The survey starts at the parapet and the stacks and ends in the rear yard. We photograph the gutters, the flashings, the covering and the outlets, and the pictures of your own roof come to you. A repair that does the job beats a replacement, and we recommend it when it does.

Once the survey is done, you get one written total as the price. What sets it is the size of the roof, the length of parapet gutter, the state of the lining, the access to the building and the number of separate roofs. It follows the survey because two shop buildings on the same street can need very different work.

During the work, the people living and trading in the building need plain information:

  • the dates the scaffold goes up and comes down
  • which sections of roof are open on which days
  • noise at the start and end of the working day
  • a phone number to call if something drips
  • the name of the person on site who answers the door

On completion, the site is clear and the waste has gone. The scaffold and its licence end on the day the licence says, so a tidy handover also means the pavement is returned to the shop and the street, and the shop's own staff can see the loading area and entrance back in use without having to ask.

Questions about a shop roof with flats above

Can the shop stay open while the roof is being re-covered?

That depends on the street. We plan the scaffold and the hoist so the shop door and the flats' entrance stay usable wherever the licence allows. Some stages, such as lifting materials onto the roof, may need the front closed for a short time, and we agree the timing with you first.

Do the flats' occupiers need a notice before the work starts?

They need warning, because the work affects their stair, their ceiling or their light. A formal notice is needed only for work that touches a party wall, and then the building owner serves it. Telling the occupiers the dates and the route in writing avoids most disputes.

Is a roof over a flat covered by the same planning rules as a house?

No. In England, the General Permitted Development Order 2015 leaves flats out of the word dwellinghouse, so flats have no householder rights. In Wales, ask the council before relying on any permitted development right at all. Listed buildings and conservation areas add their own consent.

Get your free roof quote

Tell us about the roof and we will arrange a survey.

10-year workmanship guarantee, in writing