In brief
It depends on what the work does to a wall you share, not on the fact that it is a roof job. The Party Wall etc. Act 1996 covers England and Wales, and it is the building owner who sends the notice. Work to a party wall, cutting a chimney breast away for instance, needs at least two months. A new wall on the boundary line, or excavation near a neighbour, needs at least one month. Surveyors enter only after a dissent or 14 days of silence.
Who serves the notice
You do, as the building owner, and not the roofer. Your neighbour is the adjoining owner, and the paper goes to them. People can get this wrong because they expect the roofing firm or a surveyor to send it. Neither does so for you in the ordinary run of things.
The Act reaches across England and Wales, so a semi in Hereford and a terrace in Monmouth work the same way. Questions on the Act belong with a party wall surveyor, not with building control, because the Act is separate law from Building Regulations and planning. A notice replaces neither of those, and neither of those replaces a notice.
Our part is to tell you at the survey whether the roof work touches the shared wall, and how much time to allow. If it does, we explain which kind of notice the work falls under so that you can serve it in good time. If it does not, we say that too, and the job goes ahead without one. Nobody should be sold a notice that the work does not need, and nobody should skip one that it does.
Roof-edge jobs that can trigger the Act
Most of a roof sits clear of the party wall, so some jobs need no notice at all. The ones that can bring the Act in are those that cut, build or dig near a shared or neighbouring wall.
| Work | Provision | Notice |
|---|---|---|
| Cutting back a chimney breast, jamb or flue that projects from a party wall | s2(2)(g), s3(2)(a) | At least two months |
| Cutting into a neighbour's wall to insert a flashing against a wall built up to it | s2(2)(j) | At least two months |
| Building a new wall at the line of junction | s1 | At least one month |
| Excavating close to a neighbouring building | s6 | At least one month |
The chimney breast is the example that turns up on roof jobs, because taking a stack down can lead on to the breast below it. The flashing row matters where a flat-roofed extension is butted against a neighbour's gable, and the excavation row may not touch a roof job at all. Check each row against the actual scope before assuming either way, since the wall, not the roof, decides.
When the neighbour consents, dissents or stays silent
Once the notice is served, the neighbour has three courses open.
- Consent in writing. Section 3(3)(a) lets the work proceed if the neighbouring owners and their occupiers both agree on paper.
- Dissent, which gives rise to a dispute.
- Silence. With no notice of consent inside 14 days, the Act deems the neighbour to have dissented.
GOV.UK is blunt about the last point: silence is not agreement, and you cannot treat it as such. The dispute follows automatically.
Section 10 then provides for surveyors. The two owners can appoint a single agreed surveyor, or each can appoint one and the two pick a third. GOV.UK adds that you must appoint a surveyor if you and your neighbour cannot agree. So a surveyor enters only on dissent or silence, as a way of settling a disagreement, and has no part in serving the notice itself.
Build the notice period into your plans from the outset. Two months from the day of serving is the earliest that chimney work can begin, and a dispute adds time on top.
What this means for your roof job
A re-cover that leaves the party wall untouched needs no notice. If a stack is coming down, a breast is being cut back or an extension roof ties into a neighbour's wall, your notice has to go out before the date we give you. For questions about the wording or the neighbour's reply, a party wall surveyor is the right contact. We build the roof programme around the notice period, so no scaffold is booked until the months have run.
Tell your neighbour early, and in person where you can. A notice lands better when it has been explained, and a neighbour who consents in writing saves weeks. Chimney work in particular is best talked over with the person next door before anything is posted.
Our quote is a single written price, and it sets out the scope of the roof work so you can see which parts touch the wall. Matters that can run alongside the notice include the CDM duties on a home roof job and, on a road frontage, scaffold licences in Herefordshire. The Horizon Roofing homepage shows the rest of our work around Hereford and the border towns.