In brief
The Construction (Design and Management) Regulations 2015 cover a domestic roof job in either country, and for a householder the client's main duties move to someone else. Where one contractor does the work, that contractor carries them. Where there are several, the principal contractor does. A principal designer takes them on only under a written agreement. Whichever applies, a construction phase plan must exist.
Whether you count as a domestic client
CDM 2015 is health and safety law for building work across Great Britain, so the same text governs a roof in Hereford and a roof in Abergavenny. Its starting point is a definition. The HSE says a domestic client is any individual who has construction work carried out on their own home, or the home of a family member, where the work is not part of any business.
That wording draws a clear line:
- You live in the house and want the roof re-covered: you are a domestic client.
- You are repairing a parent's house on their behalf: still a domestic client, because the home belongs to a family member.
- You let the house out, or the building is a shop or a unit: the work is part of a business, so the domestic route does not apply.
The last case is a different set of duties, and we talk it through when we visit, ahead of any written price. This page covers the householder. A householder is not left without protection under the Regulations. The duties exist, they simply travel to the people who are placed to carry them out.
Where a householder's duties go
Regulation 7(1) of the 2015 Regulations is the rule that matters. It says that where the client is a domestic client, the duties in regulations 4(1) to (7) and 6 must be carried out by one of three people. Which one depends on how the job is organised.
| How the job is set up | Who carries the duties |
|---|---|
| One contractor on the project | That contractor |
| More than one contractor | The principal contractor |
| A written agreement with a principal designer | The principal designer |
A roof job done by one firm sits in the first row. One firm re-covers the roof, so that firm holds the duties. The second row is triggered by the number of contractors, so it turns on how many firms are on site, and not on whether the job has to be notified. Extra duties follow headcount of firms, not the size of the bill.
You do not appoint anybody to this role in the ordinary case. The Regulations place the duties on the contractor automatically.
The construction phase plan
No project goes without a construction phase plan. Under regulation 15(5), where a single contractor is on the job, that contractor is the one who has to produce it, or have it produced, as soon as is practicable before the site is set up. The rule does not wait for a job to reach some size. A single slate repair is a project, and a plan applies.
For a domestic roof, the plan is a short working document. It sets out how the work will be run safely on your site. We think about these points before the scaffold arrives:
- How people get on and off the roof, and how the edges are protected.
- Where materials are stored and where the skip stands.
- How you, the household and any neighbours are kept clear of the work.
- How the site is closed up at night so nothing is left loose.
Ask to see the plan if you want to. It is not paperwork for its own sake. A roof is the highest part of the house, and the plan is where edge protection and access get thought through in advance.
What to ask when you collect quotes
Because the duties travel with the way the job is set up, a few questions at quote stage save confusion later. Ask who holds the client's CDM duties on your job, and ask how many firms will be on site. If you have a separate electrician, plasterer or builder working in the same period, that can change the answer from one contractor to more than one.
Tell us at the survey about anything else planned for the house while the roof is open, such as a loft conversion or a new boiler flue, so the arrangements are decided in advance and not on the day. Where a principal designer is involved, the written agreement is what moves the duties, so look for that paper.
Our job is to run the roof properly: the plan, the edge protection, the tidy site and the waste taken away. The legal detail sits behind a written quote with one total price, so you are not left chasing it. Scaffold arrangements on the road are a separate matter, covered in scaffolding on the road outside your house. If the job touches a neighbour's wall, a party wall notice may be needed. Everything we do is listed on the Horizon Roofing homepage.