Under section 169 of the Highways Act 1980, scaffolding on a highway needs a licence. Monmouthshire County Council's current application form sets an administration fee of £108.00, with £27.00 per week, pro rata, to extend, and asks for at least 5 working days of notice before erection. For a Monmouthshire roof job we arrange the licence with our scaffolder, so the application is in hand before we give you a start date.
When a scaffold needs a licence
The law turns on the highway, which takes in the footway and the verge as well as the carriageway. Section 169 of the Highways Act 1980 says no person shall "erect or retain on or over a highway any scaffolding or other structure which obstructs the highway" without a licence. A scaffold standing wholly inside your own boundary is not caught by that wording. One that sits on a footway, or that blocks a lane, is.
At the survey, then, we work out where the scaffold will stand. A house with a deep front garden may need no licence at all. A house whose front door opens on to the pavement is a different matter, and the question has to be answered before the job is booked.
The correct name is a scaffold licence, and it is issued by the council as highway authority. The licence belongs to that scaffold, in that position, for that period. A new date, a different position or a second elevation of the house can each call for a fresh application. For that reason the layout is fixed at the survey, and we avoid changing it once the scaffolders arrive. Tell us if a neighbour shares your access, because that changes where the scaffold can go.
Monmouthshire's fee and notice
| Item | What the council's form says |
|---|---|
| Administration fee | £108.00 |
| Extension | £27.00 per week, pro rata |
| Notice for a licence | At least 5 working days ahead of erection |
| Notice for an extension | At least 5 working days' notice |
These are the terms on the council's form as it stands now, so ask the council for the form that is current on the day you apply, since fees are reviewed. The form asks for the name of the scaffolding company, and it is returned to your local Community Hub. The council's main number is 01633 644644, and a call to it is the quickest way to ask about a particular street.
Every council sets its own fee, its own period and its own notice, and the units are not the same from one to the next. Monmouthshire's figures belong to Monmouthshire alone, so never set them beside another county's and assume they match. For the English side of the border, the figures and the notice are different again.
How we handle the application
We arrange the licence with our scaffolder. We agree that arrangement at the survey, and the paperwork is in hand before a date is confirmed. Your written quote states whether the scaffold is included, so you can see what you are paying for before you sign. Ask us to show you the sentence in the quote that says so.
From your side, the steps are short:
- We survey the roof and note where the scaffold has to stand.
- We tell you whether the footway or the verge is involved.
- The application goes to the council with the scaffold company's details.
- We confirm your start once the notice period is covered.
You do not need to fill in the form yourself or visit the Community Hub. If the council raises a question about the position, such as a bus stop, a drive entrance or a narrow lane, it comes to us and we pass on whatever matters to you. Think about neighbours' access and parking as well, because the licence covers the scaffold and does nothing for the cars that cannot park beside it. A short note through the doors a few days ahead is a good habit.
Timing, extensions and the border towns
Five working days of notice does not mean the job starts on the sixth. Weather, material delivery and the scaffolder's diary all share one calendar, and a wet week can push all three back, so we give a start date only once those line up with the council's notice.
If the job runs past its planned period, the council's form asks £27.00 per week, pro rata, for the extra time, and at least 5 working days' notice of the extension. Bad weather is one reason. We raise the extension early, so the licence never lapses with the scaffold still standing.
This page is for Monmouthshire addresses such as Monmouth, Abergavenny and Chepstow. A job in Powys is dealt with by Powys County Council on its own terms. A job on the English side is covered on our page about scaffolding on the road in Herefordshire. The quote for any Monmouthshire roof is one written total price, and our page on what a written roof quote covers explains what it should contain. The full range of our work is on the Horizon Roofing homepage.