Callout 1 of 3
Framed walls and the coverings they carry
Start at the walls. On a timber-framed house the point where wall meets roof sets the rules for every other detail above it. The 1934 Royal Commission inventory of Herefordshire visited Wigmore parish and described Chapel Farm as two-storeyed and timber-framed, with "slate-covered roofs". Its entry for the monuments numbered 5 to 22 groups them as houses of the seventeenth century, built of timber frame and covered in stone, slate or tile, unless a note says different. These are notes on named buildings, taken in the 1930s. They tell us what a few Wigmore roofs carried then and nothing about yours now, so we read the covering that is on your house, slope by slope, and say what we find.
Think of a frame as a skeleton of posts and beams, with the walls filled in between. A skeleton settles. Over the centuries the joint between timber and covering opens in a way a brick wall never allows. At the gable we test the verge, the overhang at the end wall, for gaps and for mortar bedding that has fallen out. From inside the loft we look up to the rafter feet, the point where the sloping roof timbers end at the wall. A slow leak shows there as a dark stain well before a bedroom ceiling marks, and the photographs we take from the loft go into your report.
A slipped slate or a cracked tile on a framed house is a repair. We lift what has failed, rebed the verge and put back the same kind of covering that sits on that slope, so new work and old pull the same way. Beside a brick or stone chimney stack we also check the join, since two materials move at differing rates and the lead between them has to allow for both. Where a slope has worn out, the photographs show why. Where patching is the better buy, we recommend it. Either way you receive one price, written down, and the site is cleared before we leave.
England's rules apply in Wigmore. Per the Planning Portal, a re-roof touching less than 25 per cent of the building envelope and less than 50 per cent of the roof stays below the point where an application is normally needed. The other trigger is weight: the Planning Portal names a new covering that "increases the weight of the roof covering by 15 per cent or more", and an old frame is checked before such a load goes on. Smaller jobs sit on our roof repairs page.
Noted at a framed Wigmore gable
- Verge
- Bedding mortar, and any gap to the frame
- Rafter feet
- Staining or soft timber seen from the loft
- Covering
- Slipped, cracked or missing units on each slope
- Frame junction
- Where the covering stops against the timbers
Where covering meets timber, a small gap seen early is a repair and not a re-roof.