In brief
HSE sorts asbestos work into three bands. Non-licensed work covers jobs such as lifting asbestos cement sheets out carefully and whole. Licensed work covers most asbestos insulating board. Between them sits notifiable non-licensed work, where the job needs no licence but must be notified before it starts. On roofs it arises when asbestos cement sheet has been badly damaged or broken, or when taking it off will break it. HSE's scheme covers England and Wales alike.
Three bands of asbestos work
HSE separates asbestos jobs by the risk of releasing fibre, and each band carries its own duties. A roofer meets all three on older commercial buildings, so it helps to see them side by side. The middle band is the one that surprises people, because it sounds lighter than it is.
| Band | Roof example from HSE | Plain meaning |
|---|---|---|
| Non-licensed | Asbestos cement roof sheeting taken off with care and kept whole | Weathered cement sheet that has not been badly damaged |
| Notifiable non-licensed | Cement sheet that is badly damaged or broken, or removal that will break it | No licence needed, but the work is notified first |
| Licensed | Most work on asbestos insulating board | Passed on to firms licensed for it |
Asbestos cement, shortened to AC, is the grey sheeting laid on some older units and farm buildings. Asbestos insulating board, shortened to AIB, is a softer board, seen in white soffit panels under eaves. Licensed jobs are passed on to firms that hold the licence, and the survey tells you which band yours falls in.
What tips a roof job into the notifiable band
HSE's page gives the roof triggers in plain terms. Asbestos cement falls under notifiable non-licensed work in two cases. One is where the material "has been substantially damaged or broken up", with fire or flood damage as its examples. The other is where taking it off "will mean that the material will be substantially broken up, creating significant quantities of dust and debris". HSE's own example for the second case is "dropping" an asbestos cement roof.
That second case is the one owners overlook, because the sheets may look whole on the day. If the only way to remove them is to let them fall, smash or be cut, the job is already notifiable before a bolt is undone. HSE adds one more item to the band: short-duration work "to remove asbestos insulating board as part of a refurbishment project".
This is why the survey comes first. The photographs show whether sheets are cracked, holed or broken, whether the fixings can be undone without snapping the sheet and whether the laps are sound. Those answers decide the band and the method for lifting each sheet, and they are written into the plan before the roof is touched.
What the work looks like on a commercial roof
A notifiable job is planned before anyone is on site. Where a building dates from before 2000 or was refurbished before then, HSE says to "assume that there is asbestos in it", and it states that "AC roofs are always fragile". So the first part of the plan is how people reach the work without stepping on the sheets at all.
The decisions for a roof like this include:
- how the sheets will be lifted out whole, instead of dropped
- how the floor below is cleared or protected while the work goes on
- how the waste is wrapped, bagged and held in a lockable skip
- which registered carrier takes it away, and on what paperwork
Our answer on upper-tier waste carriers covers that last point, and the one on removing asbestos cement sheets covers who may carry out which band of work. If a sheet cracks part-way through a job, the work stops and is reassessed, since it may now sit in another band. Nobody is asked to carry on while the question is open, and the change is recorded with photographs.
Where the border changes things
HSE regulates asbestos right across Great Britain. The bands, the fragility rule and the skip guidance read identically for a unit in Herefordshire and one in Monmouthshire, so no part of the NNLW definition changes at the border. The differences sit around the work, in the waste that comes off the roof and in the building approvals that follow a re-roof, and each of them is labelled below by country.
- In England, GOV.UK leaves asbestos out of the household consignment exemption, which covers domestic hazardous waste "other than asbestos waste".
- In Wales, NRW expects consignment notes from contractors who take asbestos out of a home.
- In England, the Planning Portal tests re-roofing against the building envelope and the roof, and applies it to houses.
- In Wales, the Welsh Government says re-roofing in most situations needs Building Regulations approval.
A shop or unit is a business, so household exemptions on either side do not apply to its roof. Our commercial roofing page shows where the survey sits within the work, and the price comes as a single written total, scaffold included.