A roof is one of the first things to change on an old house. A slipped stone tile gets replaced with whatever fits, a ridge is re-bedded in modern mortar, a rooflight goes in. On a listed building, each of those can be a step that needed consent first. When it did not get consent, the work is unauthorised, whoever carried it out.
The rule is not the same in both countries. England uses the Planning (Listed Buildings and Conservation Areas) Act 1990. Wales has used the Historic Environment (Wales) Act 2023 since 4 November 2024. Below, the two Acts are read in turn, with a note on how the wording reaches the owner and anyone else who has a hand in the work. It belongs with the rest of our listed and heritage roofing advice.
The council decides whether a repair needs consent. What we can do is survey the roof, photograph its present state and describe the repair in plain terms, so the question can be put to the council before any scaffold goes up.
What the two Acts actually say
In England, section 7 of the 1990 Act says that, subject to the rest of the Act, no person shall execute or cause to be executed any works for the demolition of a listed building, or for its alteration or extension "in any manner which would affect its character as a building of special architectural or historic interest, unless the works are authorised". The Act points to section 8 for how works become authorised.
In Wales, section 88(1) of the 2023 Act says "A person must not carry out works to which this section applies, or cause such works to be carried out, unless the works are authorised under section 89." Section 88(2)(a) covers alteration or extension of a listed building "in any way that would affect its character as a building of special architectural or historic interest", and section 88(2)(b) covers demolition. Section 89 provides for authorisation by listed building consent.
| Side of the border | Where it is written | The trigger |
|---|---|---|
| England | 1990 Act, section 7 | Works that would affect character, or demolition |
| Wales | 2023 Act, sections 88 and 89 | Works that would affect character, or demolition |
Both are written as prohibitions: the works must not be carried out unless authorised, so the authorisation comes first and the work follows. The test in each is character, not size. A small job can affect character, and a larger one on a plain later extension may not. The council makes that call for each building.
Who the wording reaches
Both Acts speak of a person who carries out or executes the works and of a person who causes them to happen. In England the words are "no person shall execute or cause to be executed". In Wales they are "A person must not carry out works ... or cause such works to be carried out". Neither sentence mentions owners alone, and neither is limited to the person on the roof.
How responsibility falls in a particular case is for the council and, if it comes to it, a court. A solicitor can advise on your own position. Our part is practical, and it starts at the survey. We ask what the house is listed as and what consent is already in place, and a job that needs consent waits until it is.
These questions settle the groundwork before a price is agreed:
- What does the list entry say about the roof, and when was the entry written?
- Is there an earlier consent for the roof, and does it set conditions on materials or method?
- Is the house also in a conservation area, or covered by an Article 4 direction?
- Has any earlier owner changed the roof, and is that change documented?
- Who will apply for consent, and who will keep the decision notice with the house papers?
On survey day we photograph the roof in its present state. A dated record of that kind is useful whatever the answers turn out to be, and it goes to you with the written price.
Which roof jobs can affect character
The Acts do not list roof jobs. They set the character test and leave the judgement to the council, so the same job can need consent on one house and not on another. The table below is a way of framing the question for the council. It is not a ruling.
| Roof job | Question for the council |
|---|---|
| Covering changed to a different material | Does the new material alter how the roof looks and reads? |
| Ridge or verge re-bedded | Are the bedding and fixing the same as the existing? |
| New roof window or rooflight | Does the opening change the roof's appearance? |
| Stack repaired or rebuilt | Is the stack kept as it was built? |
Materials are one place where a historic roof can lose its character. SPAB, writing about the stone and slate roofs of the region, says: "Unfortunately, many are changed to different stones or even to slates or fake stone slates." Our short answer on like-for-like repair and listed building consent works through the questions for a repair that is meant to match what was there.
Describe a job in terms of what comes off, what goes on and what stays. A consent decision is easier to reach when the old covering is photographed, the proposed covering is named and the method is set out. Ask in writing, and keep the reply with the house papers. If the council asks for a sample or a method statement, supply it before the work starts, not during it.
Permitted development is not the same as consent
Permitted development rights are a planning matter, and listed building consent is a separate control. In both countries, a listed house keeps its Class B and Class C rights, and listed building consent is needed as well. A roof job can therefore be permitted development for planning purposes and still be unauthorised for listing.
In England, Class C covers re-roofing, and it carries no condition about matching materials. In Wales, Class C.2(a) requires that the materials used "so far as practicable match" the appearance of the existing. In neither country does that settle the listing question. Our short answer on whether listed homes keep permitted development explains the split.
Two other controls sit beside listing:
- Article 4. In England, an article 4 direction is one "which enables the Secretary of State or the local planning authority to withdraw specified permitted development rights across a defined area". In Wales, the Welsh Government says such directions are found in conservation areas more than elsewhere. Check with the council whether one applies.
- Conservation areas. In England, Herefordshire Council says there are 64 in the county. A conservation area is dealt with through planning permission, not listed building consent, so check with the council what a roof job there needs. A listed building inside a conservation area meets both controls at once.
The planning side of roof windows is set out in our guide to roof window planning rules in England and Wales.
If work has started or has already been done
Stop the permanent work. Work that may be unauthorised does not become safer by being finished. A part-stripped roof is a separate problem, because an open roof lets the weather in and needs making safe. Temporary protection is not the same thing as carrying on with the job. A tarpaulin nailed through an old covering makes new holes, so hold it down with battens or weights where you can.
- Photograph the roof as it is now, from outside and from inside the loft, with the date recorded.
- Keep the paperwork: quotes, invoices, delivery notes for tiles or slates, and any messages with the builder.
- Cover the opening in a temporary, reversible way, and keep to that until the position is clear.
- Contact the council's conservation or planning team, describe what has happened and ask what it wants to see.
- Ask for the council's reply in writing, and keep it.
What follows from unauthorised work depends on the case and on the council's response, so we do not predict it. For works already done, ask the council what it holds on the property's file and what it would expect to see from you. For an unfinished job, ask what must be settled before the work resumes.
If you bought a house and found a change that nobody mentions in the papers, the same steps apply. A dated photograph of the roof taken before anything is altered is the first useful record, for you and for the council.
Where listing does not apply
Not every old roof is caught. Three situations are worth knowing before you assume that listing controls the job.
- Churches in use. In England, section 60 of the 1990 Act says the controls "shall not apply to any ecclesiastical building which is for the time being used for ecclesiastical purposes". In Wales, section 88(3)(b) excludes works in relation to an exempt religious building. Which churches count differs between the two countries.
- Scheduled monuments. In Wales, section 88(3)(a) excludes works in relation to a building which is a scheduled monument, and that has its own consent route. In England, ask the council which consent covers a building that is scheduled.
- Unlisted buildings. A house that is not listed is outside this regime, though it may sit in a conservation area, where planning rules still apply.
Do not assume a house is exempt because it is old, or listed because it looks it. The list record decides. Different buildings and monuments on one site can sit under different regimes, so ask about each separately and note the answer against each. Our answer on how to check if a house is listed shows where to look.
Whichever country the house is in, the advice holds. Check first, ask the council in writing, and let a job that needs consent wait for it. If the building is in the Bannau Brycheiniog National Park, check with the National Park Authority as well, since it handles planning there.