In brief
In Wales, scheduled monument consent is granted by the Welsh Ministers. Section 13 of the Historic Environment (Wales) Act 2023 authorises works once "written consent to carry them out has been granted by the Welsh Ministers", and section 14(1) says "An application for scheduled monument consent must be made to the Welsh Ministers." Both provisions have been in force since 4 November 2024, and the council can still decide separate planning or listed building questions on the same site.
What the 2023 Act says about who decides
The Welsh scheme sits in Part 2 of the Historic Environment (Wales) Act 2023. Section 13 sets the test. Works to a scheduled monument are authorised when the Welsh Ministers have signed off written consent and the works then follow its terms and any conditions attached to it. That written consent is what the Act calls scheduled monument consent.
Section 14 deals with the application itself, and it is short. It goes to the Welsh Ministers, names the land, and describes the works together with what they are likely to do to the monument. The Ministers may ask for further information, and they may make regulations about the form an application takes and the papers that go with it.
Section 13(2) covers works already carried out without authority. If the Ministers give their written consent afterwards, the works count as authorised from the date of that grant, not from the day they were done. That shows the route when something has gone wrong; it is no reason to start before the paperwork is settled.
How a monument differs from a listed building
A scheduled monument and a listed building are different protections, run by different decision makers. Section 88 of the same Act, the listed building provision, does not apply to works on a building that is also a scheduled monument. Those works go through the scheduled monument scheme instead, so the two consents are never both required for the same structure. A monument that is also a barn, a gatehouse or a roofless ruin is still handled as a monument, which surprises owners who assume the council holds every decision on an old building.
| Protection | Consent | Decided by |
|---|---|---|
| Scheduled monument | Scheduled monument consent | The Welsh Ministers |
| Listed building | Listed building consent | The local planning authority |
| Exempt church in use | The church body's own system | The church body |
The planning authority is the county council, or the National Park Authority inside Bannau Brycheiniog, and building control stays with the council in both cases. If you cannot tell which protection a structure carries, the council can say what is listed or scheduled at your address.
A monument in the grounds of a church
A roofer may meet a monument, on the Monmouthshire and Powys edge of our area, at a church or chapel with an old cross, tomb or earthwork in its grounds. The explanatory notes to the 2023 Act say: "if there is a scheduled monument within the curtilage of an exempt religious building, any works to that monument will require scheduled monument consent."
So the exemption for churches in use reaches the church, not the monument beside it. Scaffold feet, a skip, a ladder base or a heap of stripped slates close to the monument can each be works needing consent, depending on what they touch. For that reason our church roof survey includes the ground around the walls as well as the slopes.
Where a church roof is repaired near a monument, we expect to:
- mark out where the monument and its boundary lie before any scaffold goes up
- agree where materials and waste are stored, well away from it
- photograph the ground first, so a later question has a clear answer
- keep every ladder and hoist clear of the monument's base
Steps to take before roof work near a scheduled site
First find out whether the structure is scheduled. If something in your grounds looks old, ask the council whether it is scheduled, listed or neither, since the result tells you where the application goes. Guessing from its age or its look is no substitute.
Then give the roofing plan a clear form. A short written note of where the scaffold stands, how materials arrive and what is stored where lets the Welsh Ministers judge the likely impact, which is what section 14(2)(b) asks an application to describe. Photographs taken at the survey support the note, and a dated set also helps if anyone asks later what the ground looked like before work.
For the church roof itself, our guide to chapel and church roofs in Wales sets out the exempt list, and our guide to scheduled monuments and roof work covers both sides of the border. Our listed and heritage roofing page explains how we survey. When the written price arrives it comes as a single sum, and the quote should tell you whether the scaffold has been counted.